plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
27 úsekov |
254,2 km |
2 - 8 |
4 528 mil. € |
156,0 min. |
2,3 |
2,8 |
||||||
1 | ![]() | D1 | 14,9 km | 4 | 341 mil. € | 20,0 min. | 1 | 1 | ||||
2 | ![]() | D1 | 13,5 km | 4 | 555 mil. € | 17,5 min. | 1 | 2 | ||||
3 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2 | ||||||
4 | ![]() | D4 | 22,6 km | 4 - 6 | 1 | 2 | ||||||
5 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 100 % | ||||
6 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 11,5 min. | 2 | 2 | 100 % | |||
7 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 7,0 min. | 3 | 4 | 100 % | |||
8 | ![]() | R3 | 4,4 km | 2 | 70 mil. € | 7,0 min. | 2 | 2 | 100 % | |||
9 | ![]() | R4 | 14,3 km | 4 | 202 mil. € | 2 | 1 | 100 % | ||||
10 | ![]() | D1 | 3,5 km | 8 | 149 mil. € | 1 | 1 | 99 % | ||||
11 | ![]() | R4 | 10,2 km | 4 | 299 mil. € | 1 | 3 | 98 % | ||||
12 | ![]() | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | 7 % | ||||
13 | ![]() | R2 | 6,8 km | 4 | 171 mil. € | 3 | 3 | 99 % | ||||
14 | ![]() | R2 | 6,2 km | 2 | 105 mil. € | 5,5 min. | 2 | 2 | 73 % | |||
15 | ![]() | R7 | 9,4 km | 4 | 191 mil. € | 7,0 min. | 4 | 5 | 0 % | |||
16 | ![]() | D1 | 3,8 km | 2 | 57 mil. € | 3 | 5 | 30 %, pozastavené | ||||
17 | ![]() | R2 | 8,3 km | 2 | 169 mil. € | 7,5 min. | 2 | 2 | 70 % | |||
18 | ![]() | R7 | 14,3 km | 2 | 172 mil. € | 4 | 4 | 0 % | ||||
19 | ![]() | R2 | 14,1 km | 2 | 272 mil. € | 14,5 min. | 3 | 2 | 63 % | |||
20 | ![]() | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 0 % | ||||
21 | ![]() | R4 | 8,2 km | 2 | 94 mil. € | 7,0 min. | 3 | 3 | 0 % | |||
22 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 5,5 min. | 2 | 2 | 0 % | |||
23 | ![]() | R3 | 8,3 km | 2 | 199 mil. € | 11,0 min. | 2 | 3 | 0 % | |||
24 | ![]() | R2 | 20,7 km | 2 | 211 mil. € | 15,0 min. | 4 | 4 | 0 % | |||
25 | ![]() | R2 | 10,6 km | 2 | 125 mil. € | 9,0 min. | 4 | 4 | 0 % | |||
26 | ![]() | R2 | 11,5 km | 2 | 235 mil. € | 11,0 min. | 2 | 4 | 0 % | |||
27 | ![]() | D3 | 3,1 km | 4 | 60 mil. € | 5 | 5 | 0 % | ||||
27 úsekov |
254,2 km |
2 - 8 |
4 528 mil. € |
156,0 min. |
2,3 |
2,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku