dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 6/2014 | D1 | 13,5 km | 4 | 2 365 m | 555 mil. € | 9,9 min. | 17 773 - 28 598 | 1 | 2 | 9/2008 | ||||
2 | 7/2016 | D4 | 4,4 km | 4 - 6 | 1 | 2 | 2/2017 | ||||||||
3 | 7/2016 | D4 | 22,6 km | 4 - 6 | 17 299 - 80 582 | 1 | 2 | 8/2017 | |||||||
4 | 7/2019 | R4 | 4,3 km | 4 | 884 m | 179 mil. € | 13 956 - 15 885 | 1 | 3 | 8/2016 | |||||
5 | 8/2019 | R2 | 13,5 km | 4 | 1 631 m | 142 mil. € | 5,0 min. | 6 702 - 7 582 | 2 | 2 | 6/2018 | ||||
6 | 3/2020 | R2 | 9,1 km | 4 | 2 553 m | 267 mil. € | 2,6 min. | 6 367 - 8 795 | 3 | 4 | |||||
7 | 3/2021 | R3 | 4,4 km | 2 | 1 568 m | 70 mil. € | 3,6 min. | 8 388 - 9 538 | 2 | 2 | 2/2012 | ||||
8 | 1. | 10/2021 | R4 | 14,3 km | 4 | 1 036 m | 202 mil. € | 8 106 - 43 990 | 2 | 1 | 7/2019 | ||||
9 | 6. | 7/2023 | R2 | 6,8 km | 4 | 1 556 m | 171 mil. € | 10 257 - 43 990 | 3 | 3 | 3/2022 | ||||
92,9 km |
2 - 6 |
11 593 m |
1 587 mil. € |
21,2 min. |
1,8 |
2,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku