dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
151,4 km |
4 - 8 |
4 178 mil. € |
1,0 |
1,6 |
11/2015 - 10/2021 | ||||||||||
1 | 3. | 3/2022 | D1 | 3,5 km | 8 | D 41/120 | Ivanka sever | 149 mil. € | 11 991 | 1 | 1 | ||||
2 | 12/2013 | D1 | 14,9 km | 4 | D 26,5/100 | Hubová, Likavka, Ivachnová | 341 mil. € | 4 597 | 1 | 1 | |||||
3 | 7/2016 | D4 | 4,4 km | 4 - 6 | D 33,5/120, D 26,5/120 | Čierna voda, Rača | 1 | 2 | |||||||
4 | 7/2016 | D4 | 22,6 km | 4 - 6 | D 33,5/120, D 26,5/120 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 1 | 2 | |||||||
5 | 7/2016 | R7 | 8,4 km | 4 | R 31,5/120 | Dunajská Lužná | 1 | 1 | 7/2020 (0,0) | ||||||
6 | 6/2014 | D1 | 13,5 km | 4 | D 26,5/100 | Lietavská Lúčka | 555 mil. € | Trasu od Martina po križovatku Rondel v centre Žiliny tento úsek D1 s tunelom Višňové skráti o 2,5 km a zrýchli v priemere o cca 11 minút pre osobné a 9 minút pre nákladné vozidlá. Pre tranzit medzi Martinom a Kysucami bude skrátenie 1 km a časová úspora cca 8 minút. | 10 992 | 1 | 2 | ||||
7 | 31. | 11/2026 | D3 | 4,0 km | 4 | D 24,5/80 | 179 mil. € | 7 452 | 1 | 2 | |||||
8 | 7/2019 | R4 | 4,3 km | 4 | R 24,5/100 | Prešov - sever | 179 mil. € | 5 339 | 1 | 3 | |||||
9 | 4. | 9/2022 | R4 | 10,2 km | 4 | R 24,5/100 | Kapušany | 299 mil. € | 4 389 | 1 | 3 | ||||
10 | 6/2017 | D1 | 7,9 km | 4 | D 26,5/100 | Prešov západ, Prešov juh | 434 mil. € | 1 | 2 | 10/2021 | |||||
11 | 7/2016 | R7 | 6,4 km | 4 - 6 | R 31,5/120 | Prievoz | 1 | 1 | 10/2021 | ||||||
12 | 12/2017 | D1 | 2,6 km | 4 | R 22,5/80 | 39 mil. € | 1 | 1 | 1/2021 (0,0) | ||||||
13 | 12/2013 | R2 | 10,4 km | 4 | 1 | 1 | 11/2015 | ||||||||
14 | 7. | 2/2024 | D1 | 13,5 km | 4 | D 26,5/100 | Turany 2, Hubová | 1 235 mil. € | 6 458 | 1 | 1 | ||||
15 | 8/2014 | R2 | 7,9 km | 4 | 88 mil. € | 1 | 1 | 5/2017 | |||||||
16 | 12/2016 | D3 | 5,7 km | 4 | D 24,5/80 | Čadca Podzávoz, Čadca Bukov | 269 mil. € | 1 | 2 | 12/2020 (0,0) | |||||
17 | 27. | 5/2026 | D3 | 11,2 km | 4 | D 24,5/80 | Brodno, Kysucké Nové Mesto | 410 mil. € | 1 | 1 | |||||
151,4 km |
4 - 8 |
4 178 mil. € |
1,0 |
1,6 |
11/2015 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku