plánovaný
|
odhad NDS
|
stavebné práce
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||
25 úsekov |
252,2 km |
2 - 8 |
4 343 mil. € |
1 042,7 mil. € |
2,0 |
2,3 |
10/2016 - 8/2036 |
3. - 47. | ||||
1 | ![]() | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | 4/2026 (+3,7) | 27. | |||
2 | ![]() | D1 | 10,6 km | 8 | 234 mil. € | 2 | 1 | 6/2030 (+6,9) | ||||
3 | ![]() | D1 | 14,4 km | 4 | 241 mil. € | 197,4 mil. € | 2 | 2 | 12/2019 | |||
4 | ![]() | R2 | 6,2 km | 2 | 105 mil. € | 2 | 2 | 3/2026 (+4,7) | 34. | |||
5 | ![]() | D1 | 18,2 km | 4 | 192 mil. € | 2 | 2 | 8/2036 (+7,9) | 8. | |||
6 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 10/2028 (+4,1) | 16. | |||
7 | ![]() | R2 | 9,6 km | 2 | 112 mil. € | 2 | 4 | 3/2031 (+5,9) | 43. | |||
8 | ![]() | R7 | 17,4 km | 4 | 2 | 3 | 7/2020 (+0,0) | |||||
9 | ![]() | R4 | 6,5 km | 2 | 116 mil. € | 2 | 3 | 6/2030 (+3,7) | 14. | |||
10 | ![]() | D1 | 11,3 km | 4 | 517 mil. € | 427,2 mil. € | 2 | 3 | 2021 (+2,1) | |||
11 | ![]() | R4 | 14,3 km | 4 | 202 mil. € | 2 | 1 | 10/2024 (+2,6) | ||||
12 | ![]() | R3 | 6,5 km | 2 | 70 mil. € | 2 | 2 | 7/2026 (+2,7) | 47. | |||
13 | ![]() | D3 | 10,8 km | 4 | 309 mil. € | 2 | 4 | 1/2029 (+3,0) | 5. | |||
14 | ![]() | R4 | 4,0 km | 4 | 105 mil. € | 2 | 2 | 8/2029 (+3,8) | 3. | |||
15 | ![]() | R2 | 16,0 km | 4 | 277 mil. € | 2 | 2 | 10/2028 (+3,2) | 23. | |||
16 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 2 | 2 | 2021 (+1,1) | ||||
17 | ![]() | R3 | 8,3 km | 2 | 199 mil. € | 2 | 3 | 10/2028 (+4,1) | 17. | |||
18 | ![]() | R2 | 11,5 km | 2 | 235 mil. € | 2 | 4 | 9/2031 (+5,4) | 30. | |||
19 | ![]() | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 1/2027 (+5,0) | ||||
20 | ![]() | R4 | 7,0 km | 2 | 122 mil. € | 2 | 2 | 6/2030 (+3,7) | 15. | |||
21 | ![]() | R2 | 9,6 km | 2 | 88,2 mil. € | 2 | 1 | 10/2016 | ||||
22 | ![]() | D3 | 12,3 km | 2 | 377 mil. € | 329,9 mil. € | 2 | 2 | 6/2017 | |||
23 | ![]() | R3 | 4,4 km | 2 | 70 mil. € | 2 | 2 | 8/2022 (+2,2) | ||||
24 | ![]() | R2 | 8,3 km | 2 | 169 mil. € | 2 | 2 | 8/2026 (+5,1) | 40. | |||
25 | ![]() | R2 | 17,5 km | 4 | 287 mil. € | 2 | 2 | 7/2034 (+10,0) | ||||
25 úsekov |
252,2 km |
2 - 8 |
4 343 mil. € |
1 042,7 mil. € |
2,0 |
2,3 |
10/2016 - 8/2036 |
3. - 47. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku