dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
252,2 km |
2 - 8 |
4 343 mil. € |
2,0 |
2,3 |
0.1 - 1.22 | |||||||
1 | 10/2013 | D3 | 12,3 km | 2 | 377 mil. € | 2 | 2 | |||||
2 | 1/2014 | D1 | 11,3 km | 4 | 517 mil. € | 2 | 3 | |||||
3 | 1/2014 | R2 | 9,6 km | 2 | 2 | 1 | ||||||
4 | 7/2016 | R7 | 17,4 km | 4 | Šamorín, Holice | 2 | 3 | |||||
5 | 11/2016 | D1 | 14,4 km | 4 | Budimír (Košice-Sever), Košické Olšany, Bidovce | 241 mil. € | 2 | 2 | ||||
6 | 8/2019 | R2 | 13,5 km | 4 | Mýtna | 142 mil. € | 2 | 2 | ||||
7 | 3/2021 | R3 | 4,4 km | 2 | Nižná,
Nižná - sever | 70 mil. € | 2 | 2 | ||||
8 | 1. | 10/2021 | R4 | 14,3 km | 4 | Košice-juh, Krásna, Hrašovík | 202 mil. € | 2 | 1 | nedostupný údaj | ||
9 | 5. | 4/2023 | R1 | 8,1 km | 4 | Šalková | 173 mil. € | 2 | 3 | 0,60 | ||
10 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 105 mil. € | 2 | 2 | 0,46 | |||
11 | 12. | 7/2024 | R3 | 6,5 km | 2 | privádzač Krupina | 70 mil. € | 2 | 2 | 0,10 | ||
12 | 13. | 8/2024 | R2 | 8,3 km | 2 | Zacharovce, Bátka | 169 mil. € | 2 | 2 | 0,23 | ||
13 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | nedostupný údaj | |||
14 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | Dlhá nad Oravou | 77 mil. € | 2 | 2 | 0,96 | ||
15 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | Podbiel | 199 mil. € | 2 | 3 | 0,94 | ||
16 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | Trenčianske Mitice | 277 mil. € | 2 | 2 | 0,65 | ||
17 | 25. | 1/2026 | D3 | 10,8 km | 4 | Krásno nad Kysucou | 309 mil. € | 2 | 4 | 0,43 | ||
18 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | Lipníky | 105 mil. € | 2 | 2 | 0,78 | ||
19 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | Senec | 234 mil. € | 2 | 1 | nedostupný údaj | ||
20 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | Kuková | 116 mil. € | 2 | 3 | 1,03 | ||
21 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | Okrúhle | 122 mil. € | 2 | 2 | 0,86 | ||
22 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | Nováky - západ | 112 mil. € | 2 | 4 | 0,22 | ||
23 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 2 | 4 | 0,54 | |||
24 | 59. | 7/2031 | R2 | 17,5 km | 4 | Rákoš, Zvolenská Slatina | 287 mil. € | 2 | 2 | nedostupný údaj | ||
25 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | Hriadky, Pozdišovce | 192 mil. € | 2 | 2 | 1,22 | ||
252,2 km |
2 - 8 |
4 343 mil. € |
2,0 |
2,3 |
0.1 - 1.22 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku