dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||||
21 úsekov |
256,0 km |
2 - 6 |
22 209 m |
5 955 mil. € |
16,7 min. |
3 769 - 54 519 | 3,0 |
3,3 |
3/2024 - 8/2037 |
||||||||||
1 | 3/2020 | R2 | 9,1 km | 4 | 2 553 m | Kriváň | 267 mil. € | 0,5 min. | 8 780 - 11 203 | 3 | 4 | 7,0 | 3/2024 | ||||||
2 | 6. | 7/2023 | R2 | 6,8 km | 4 | 1 556 m | Ludvíkov Dvor, Haniska | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 9,0 | 7/2026 | ||||||
3 | 10. | 4/2024 | D1 | 3,8 km | 2 | 1 030 m | 57 mil. € | 10 312 | 3 | 5 | 8,0 | 4/2027 | |||||||
4 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 1 035 m | Rožňava, Jablonov nad Turňou | 272 mil. € | 4,5 min. | 5 792 - 7 064 | 3 | 2 | 8,0 | 12/2029 | |||||
5 | 19. | 6/2025 | R4 | 8,2 km | 2 | 453 m | Svidník sever | 94 mil. € | 1,2 min. | 4 001 | 3 | 3 | 7,0 | 6/2027 | |||||
6 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 145 m | 59 mil. € | 0,5 min. | 12 862 | 3 | 4 | 6,0 | 10/2028 | ||||||
7 | 24. | 12/2025 | R2 | 6,1 km | 4 | 1 462 m | Trenčín juh, Trenčianska Turná | 143 mil. € | -0,1 min. | 12 157 | 3 | 4 | 7,0 | 12/2028 | |||||
8 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 4,0 | 6/2033 | |||||||||
9 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 554 m | Moldava nad Bodvou, Šaca | 224 mil. € | 0,3 min. | 10 140 - 11 010 | 3 | 5 | 5,0 | 12/2029 | |||||
10 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 4 086 m | Slovenská Ľupča, Korytnica | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 4,0 | 2/2031 | ||||||
11 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | 5,0 | 9/2032 | ||||||
12 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 652 m | Šahy | 63 mil. € | 9 492 - 10 279 | 3 | 2 | 3,0 | 11/2030 | ||||||
13 | 46. | 3/2029 | D1 | 7,3 km | 4 | 660 m | 321 mil. € | 0,8 min. | 10 359 | 3 | 3 | 3,0 | 9/2033 | ||||||
14 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 1 826 m | Giraltovce | 124 mil. € | 2,8 min. | 3 769 - 3 897 | 3 | 3 | 4,0 | 5/2033 | |||||
15 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 3,0 | 6/2036 | ||||||||
16 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 1 024 m | Martin, Rakovo | 191 mil. € | 14 233 - 18 874 | 3 | 3 | 3,0 | 6/2034 | ||||||
17 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 1 040 m | Široká, Jasenová, v mestskom variante tiež Kocmáľ (Mokraď) a Dolný Kubín stred | 129 mil. € | 3,3 min. | 5 586 - 10 745 | 3 | 2 | 3,0 | 8/2034 | |||||
18 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 165 m | Dargov | 418 mil. € | 3,1 min. | 9 503 - 9 802 | 3 | 3 | 2,0 | 8/2036 | |||||
19 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 383 m | Michalovce | 162 mil. € | -0,3 min. | 10 444 - 14 783 | 3 | 3 | 2,0 | 8/2036 | |||||
20 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 2 641 m | Sklené,
Ráztočno | 305 mil. € | 3 | 3 | 2,0 | 8/2037 | |||||||
21 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | 944 m | Svrčinovec, Svrčinovec - hranica | 54 mil. € | 7 972 | 3 | 4 | 4,0 | |||||||
21 úsekov |
256,0 km |
2 - 6 |
22 209 m |
5 955 mil. € |
16,7 min. |
3 769 - 54 519 | 3,0 |
3,3 |
3/2024 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku