dátum |
plánovaný
|
odhad NDS
|
pozemky
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
21 úsekov |
256,0 km |
2 - 6 |
5 955 mil. € |
251,0 mil. € |
3,0 |
3,3 |
|||||||||
1 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 2,5 mil. € | 3 | 4 | 11/2004 | |||||
2 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 4 | 171 mil. € | 35,4 mil. € | 3 | 3 | 6/2014 | Preberacie konanie po kompletnom dodaní dokumentácie na ponuku v podrobnosti dokumentácie na realizáciu stavby. | |||
3 | 10. | 4/2024 | ![]() | D1 | 3,8 km | 2 | 57 mil. € | 2,5 mil. € | 3 | 5 | žiadna | ||||
4 | 16. - 17. | 12/2024 | ![]() | R2 | 14,1 km | 2 | 272 mil. € | 10,4 mil. € | 3 | 2 | 9/2009 | žiadna | |||
5 | 19. | 6/2025 | ![]() | R4 | 8,2 km | 2 | 94 mil. € | 2,1 mil. € | 3 | 3 | 1/2000 | žiadna | |||
6 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 8,7 mil. € | 3 | 4 | 11/2003 | Vypracovanie dokumentácie na stavebné povolenie, jej pripomienkovanie a preberanie. | |||
7 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 26,4 mil. € | 3 | 4 | 11/2003 | Dobieha vypracovanie dokumentácií na zmenu územného rozhodnutia a na stavebné povolenie. Ide však o plytvanie kapacitami a zdrojmi, keďže realizácia nákladného riešenia s malými prínosmi je prakticky vylúčená - podľa priorít schválených vládou v septembri 2020 je projekt až na 97. mieste zo 100 hodnotených. | |||
8 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 2,9 mil. € | 3 | 4 | 12/2010 | Od roku 2017 prebieha proces posúdenia vplyvov na životné prostredie (EIA). | |||
9 | 32. - 33. | 12/2026 | ![]() | R2 | 18,0 km | 2 | 224 mil. € | 22,6 mil. € | 3 | 5 | 6/2016 | žiadna | |||
10 | 37. - 38. | 2/2028 | ![]() | R1 | 14,9 km | 4 | 785 mil. € | 7,9 mil. € | 3 | 3 | 4/2010 | žiadna | |||
11 | 39. - 40. | 3/2028 | ![]() | D1 | 19,9 km | 6 | 321 mil. € | 37,5 mil. € | 3 | 2 | 12/2009 | žiadna | |||
12 | 42. - 43. | 11/2028 | ![]() | R3 | 5,0 km | 2 | 63 mil. € | 1,3 mil. € | 3 | 2 | 11/2018 | žiadna | |||
13 | 46. | 3/2029 | ![]() | D1 | 7,3 km | 4 | 321 mil. € | 0,5 mil. € | 3 | 3 | 8/2013 | žiadna | |||
14 | 50. - 52. | 5/2030 | ![]() | R4 | 7,5 km | 2 | 124 mil. € | 4,8 mil. € | 3 | 3 | žiadna | ||||
15 | 57. - 58. | 6/2031 | ![]() | R8 | 54,9 km | 4 | 1 020 mil. € | 28,6 mil. € | 3 | 5 | 4/2010 | žiadna | |||
16 | 57. - 58. | 6/2031 | ![]() | R3 | 14,0 km | 4 | 191 mil. € | 19,0 mil. € | 3 | 3 | 9/2010 | žiadna | |||
17 | 60. - 61. | 8/2031 | ![]() | R3 | 10,9 km | 2 | 129 mil. € | 6,0 mil. € | 3 | 2 | žiadna | ||||
18 | 64. - 68. | 8/2033 | ![]() | D1 | 12,6 km | 4 | 418 mil. € | 7,0 mil. € | 3 | 3 | žiadna | ||||
19 | 64. - 68. | 8/2033 | ![]() | D1 | 12,1 km | 4 | 162 mil. € | 7,0 mil. € | 3 | 3 | žiadna | ||||
20 | 69. - 70. | 8/2034 | ![]() | R3 | 14,0 km | 2 | 305 mil. € | 15,0 mil. € | 3 | 3 | 2/2020 | žiadna | |||
21 | 71. - 78. | po 2040 | ![]() | R5 | 1,7 km | 2 | 54 mil. € | 2,9 mil. € | 3 | 4 | 10/2009 | žiadna | |||
21 úsekov |
256,0 km |
2 - 6 |
5 955 mil. € |
251,0 mil. € |
3,0 |
3,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku