dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
21 úsekov |
256,0 km |
2 - 6 |
4 460 m |
5 955 mil. € |
3,0 |
3,3 |
7/2024 - 8/2037 | ||||||||
1 | 3/2020 | R2 | 9,1 km | 4 | 212 m | 267 mil. € | 6 367 - 8 795 | 2 408 - 2 413 | 3 | 4 | 2024 (+2,8) | ||||
2 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 7 618 | 2 741 | 3 | 3 | 9/2033 (+5,8) | ||||
3 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 53 m | 418 mil. € | 7 955 - 8 161 | 1 548 - 1 641 | 3 | 3 | 8/2036 (+7,9) | |||
4 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 36 147 - 46 904 | 6 627 - 7 615 | 3 | 2 | 9/2032 (+5,6) | ||||
5 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||||
6 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 60 m | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | |||||
7 | 6. | 7/2023 | R2 | 6,8 km | 4 | 1 169 m | 171 mil. € | 10 257 - 43 990 | 1 373 - 6 905 | 3 | 3 | 7/2026 (+4,3) | |||
8 | 24. | 12/2025 | R2 | 6,1 km | 4 | 178 m | 143 mil. € | 9 342 | 2 815 | 3 | 4 | 12/2028 (+4,3) | |||
9 | 19. | 6/2025 | R4 | 8,2 km | 2 | 34 m | 94 mil. € | 2 304 | 1 697 | 3 | 3 | 6/2027 (+4,7) | |||
10 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 433 m | 191 mil. € | 11 208 - 15 489 | 3 025 - 3 385 | 3 | 3 | 6/2034 (+7,0) | |||
11 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 1 015 m | 224 mil. € | 8 325 - 9 049 | 1 815 - 1 961 | 3 | 5 | 12/2029 (+2,8) | |||
12 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 3 190 - 9 726 | 906 - 2 145 | 3 | 5 | 6/2036 (+2,3) | ||||
13 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 164 m | 129 mil. € | 4 234 - 8 517 | 1 352 - 2 228 | 3 | 2 | 8/2034 (+2,1) | |||
14 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 154 m | 162 mil. € | 8 909 - 13 062 | 1 535 - 1 721 | 3 | 3 | 8/2036 (+7,7) | |||
15 | 10. | 4/2024 | D1 | 3,8 km | 2 | 57 mil. € | 9 024 | 1 288 | 3 | 5 | 4/2027 (+4,1) | ||||
16 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 137 m | 124 mil. € | 2 053 - 2 240 | 1 529 - 1 844 | 3 | 3 | 5/2033 (+6,1) | |||
17 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 60 m | 272 mil. € | 4 549 - 5 778 | 1 175 - 1 286 | 3 | 2 | 12/2029 (+5,4) | |||
18 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 446 m | 785 mil. € | 6 735 - 10 692 | 1 405 - 2 512 | 3 | 3 | 2/2031 (+6,9) | |||
19 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | 128 m | 54 mil. € | 4 717 | 3 255 | 3 | 4 | 3/2025 (0,0) | |||
20 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 61 m | 59 mil. € | 10 033 | 2 829 | 3 | 4 | 10/2028 (+4,2) | |||
21 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 157 m | 63 mil. € | 8 049 - 8 636 | 1 443 - 1 643 | 3 | 2 | 11/2030 (+5,2) | |||
21 úsekov |
256,0 km |
2 - 6 |
4 460 m |
5 955 mil. € |
3,0 |
3,3 |
7/2024 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku