dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
44 úsekov |
585,4 km |
2 - 6 |
10 879 mil. € |
3,5 |
3,4 |
||||||||
1 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 3 | 5 | ||||
2 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | 227 mil. € | 4 | 4 | ||||
3 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 191 mil. € | 4 | 5 | ||||
4 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | 161 mil. € | 4 | 5 | ||||
5 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | 172 mil. € | 4 | 4 | ||||
6 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R 11,5/100 (80) | 182 mil. € | 4 | 3 | ||||
7 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R 11,5/100 (80) | 222 mil. € | 4 | 3 | ||||
8 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | R 11,5/70 | 54 mil. € | 3 | 4 | ||||
9 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 133 mil. € | 4 | 3 | ||||
10 | 19. | 6/2025 | R4 | 8,2 km | 2 | R 24,5/100, plánované v 1/2-profile | 94 mil. € | 3 | 3 | ||||
11 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 124 mil. € | 3 | 3 | ||||
12 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 101 mil. € | 4 | 3 | ||||
13 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | R 24,5/100, plánované v 1/2-profile | 129 mil. € | 4 | 3 | ||||
14 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | R 11,5/80 (60) | 94 mil. € | 4 | 2 | ||||
15 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 305 mil. € | 3 | 3 | ||||
16 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | R 24,5/120 (100) | 191 mil. € | 3 | 3 | ||||
17 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 71 mil. € | 4 | 3 | ||||
18 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | R 11,5/80 (60) | 129 mil. € | 3 | 2 | ||||
19 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 92 mil. € | 4 | 2 | ||||
20 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 611 mil. € | 4 | 4 | ||||
21 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 63 mil. € | 3 | 2 | ||||
22 | 6. | 7/2023 | R2 | 6,8 km | 4 | R 24,5/100 | 171 mil. € | 3 | 3 | ||||
23 | 3/2020 | R2 | 9,1 km | 4 | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | 267 mil. € | 3 | 4 | |||||
24 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 143 mil. € | 3 | 4 | ||||
25 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 4 | 4 | ||||
26 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 224 mil. € | 3 | 5 | ||||
27 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 662 mil. € | 4 | 4 | ||||
28 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | 125 mil. € | 4 | 4 | ||||
29 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 272 mil. € | 3 | 2 | ||||
30 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 3 | 4 | ||||
31 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | R 24,5/80 | 406 mil. € | 4 | 4 | ||||
32 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | R 24,5/80 | 339 mil. € | 4 | 4 | ||||
33 | 11. | 6/2024 | R1 | 2,7 km | 4 | R 24,5/80 | 155 mil. € | 4 | 3 | ||||
34 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | 100 mil. € | 4 | 3 | ||||
35 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | R 24,5/80 | 785 mil. € | 3 | 3 | ||||
36 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | ||||
37 | 6/2014 | D3 | 4,3 km | 4 | D 24,5/80 | 269 mil. € | 4 | 2 | 12/2017 | ||||
38 | 46. | 3/2029 | D1 | 7,3 km | 4 | 26,5/100 | 321 mil. € | 3 | 3 | ||||
39 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | D 26,5/120
(100) | 418 mil. € | 3 | 3 | ||||
40 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D 33,5/120 | 321 mil. € | 3 | 2 | ||||
41 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | D 26,5/120
(100) | 139 mil. € | 4 | 3 | ||||
42 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | D 26,5/120
(100) | 162 mil. € | 3 | 3 | ||||
43 | 10. | 4/2024 | D1 | 3,8 km | 2 | R 11,5/80 | 57 mil. € | 3 | 5 | ||||
44 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | D 26,5/120
(100) | 136 mil. € | 4 | 3 | ||||
44 úsekov |
585,4 km |
2 - 6 |
10 879 mil. € |
3,5 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku