dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
329,4 km |
2 - 4 |
45 725 m |
4 925 mil. € |
30,2 min. |
4,0 |
3,4 |
|||||||||
1 | 6/2014 | D3 | 4,3 km | 4 | 1 912 m | 269 mil. € | 4 | 2 | 12/2017 | ||||||
2 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 362 m | 191 mil. € | 2,5 min. | 4 | 5 | 4/2020 | 7/2023 | |||
3 | 11. | 6/2024 | R1 | 2,7 km | 4 | 221 m | 155 mil. € | 4 | 3 | 2/2020 | 4/2023 | ||||
4 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 2 006 m | 227 mil. € | 4 | 4 | 9/2020 | 11/2023 | ||||
5 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | 2 006 m | 172 mil. € | 4 | 4 | 9/2020 | 11/2023 | ||||
6 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | 420 m | 161 mil. € | 4 | 5 | 1/2021 | 4/2024 | ||||
7 | 26. | 4/2026 | R2 | 20,7 km | 2 | 2 594 m | 211 mil. € | 1,9 min. | 4 | 4 | 1/2011 | 8/2024 | |||
8 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 1 041 m | 125 mil. € | 2,3 min. | 4 | 4 | 2/2009 | 3/2025 | |||
9 | 30. | 10/2026 | R1 | 4,6 km | 4 | 1 225 m | 100 mil. € | 4 | 3 | 7/2023 | 10/2025 | ||||
10 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 4 546 m | 129 mil. € | 1,8 min. | 4 | 3 | 2/2023 | 11/2026 | |||
11 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 820 m | 71 mil. € | 4 | 3 | 1/2025 | 2/2028 | ||||
12 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 2 907 m | 133 mil. € | 2,6 min. | 4 | 3 | 7/2024 | 5/2028 | |||
13 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 1 017 m | 101 mil. € | 1,2 min. | 4 | 3 | 7/2024 | 5/2028 | |||
14 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 2 970 m | 182 mil. € | 4 | 3 | 3/2025 | 2/2029 | ||||
15 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 3 310 m | 222 mil. € | 4 | 3 | 3/2025 | 2/2029 | ||||
16 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 907 m | 406 mil. € | 4 | 4 | 11/2026 | 6/2029 | ||||
17 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 1 752 m | 339 mil. € | 4 | 4 | 11/2026 | 6/2029 | ||||
18 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 178 m | 94 mil. € | 1,4 min. | 4 | 2 | 3/2026 | 1/2030 | |||
19 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 180 m | 139 mil. € | 8,9 min. | 4 | 3 | 11/2027 | 8/2031 | |||
20 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 343 m | 136 mil. € | 7,6 min. | 4 | 3 | 11/2027 | 8/2031 | |||
21 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 2 587 m | 662 mil. € | 4 | 4 | 4/2029 | 2/2033 | ||||
22 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 95 m | 92 mil. € | 4 | 2 | ||||||
23 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | 12 326 m | 611 mil. € | 4 | 4 | ||||||
329,4 km |
2 - 4 |
45 725 m |
4 925 mil. € |
30,2 min. |
4,0 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku