dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
|
+ posun v rokoch
za posledné cca 4 roky | |||||||
398,5 km |
2 - 8 |
6 808 mil. € |
2,7 |
2,9 |
3 - 78 |
11/2015 - po 2040 |
11/2015 - 10/2021 | |||||||
1 | 12/2013 | 14,9 km | 4 | 341 mil. € | 1 | 1 | 2023 (+1,0) | |||||||
2 | 12/2013 | 10,4 km | 4 | 1 | 1 | 11/2015 | 11/2015 | |||||||
3 | 6/2014 | 13,5 km | 4 | 555 mil. € | 1 | 2 | 2024 (+4,0) | |||||||
4 | 8/2014 | 7,9 km | 4 | 88 mil. € | 1 | 1 | 5/2017 | 5/2017 | ||||||
5 | 7/2016 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | ||||||||
6 | 7/2016 | 22,6 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | ||||||||
7 | 7/2016 | 8,4 km | 4 | 1 | 1 | 7/2020 (–1,0) | 7/2020 (0,0) | |||||||
8 | 7/2016 | 6,4 km | 4 - 6 | 1 | 1 | 10/2021 (+0,3) | 10/2021 | |||||||
9 | 12/2016 | 5,7 km | 4 | 269 mil. € | 1 | 2 | 6/2014 | 2021 (+0,5) | 12/2020 (0,0) | |||||
10 | 6/2017 | 7,9 km | 4 | 434 mil. € | 1 | 2 | 5/2015 | 7/2021 (0,0) | 10/2021 | |||||
11 | 12/2017 | 2,6 km | 4 | 39 mil. € | 1 | 1 | 0,0 | 2021 (+2,2) | 1/2021 (0,0) | |||||
12 | 7/2019 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 0,0 | 5/2015 | 2023 (+2,0) | |||||
13 | 3. | 3/2022 | 3,5 km | 8 | 149 mil. € | 1 | 1 | 1,0 | 3 | 9/2025 (+4,6) | ||||
14 | 4. | 9/2022 | 10,2 km | 4 | 299 mil. € | 1 | 3 | 1,0 | 5/2015 | 4 | 1/2027 (+4,8) | |||
15 | 7. | 2/2024 | 13,5 km | 4 | 1 235 mil. € | 1 | 1 | 3,0 | 7 | 12/2030 (+4,5) | ||||
16 | 27. | 5/2026 | 11,2 km | 4 | 410 mil. € | 1 | 1 | 4,0 | 6/2014 | 27 | 5/2029 (+5,1) | |||
17 | 31. | 11/2026 | 4,0 km | 4 | 179 mil. € | 1 | 2 | 4,0 | 6/2014 | 31 | 11/2030 (+6,4) | |||
18 | 37. - 38. | 2/2028 | 7,8 km | 2 | 73 mil. € | 5 | 4 | 6,0 | 4/2015 | 38 | 2/2031 (+4,1) | |||
19 | 44. - 45. | 2/2029 | 18,0 km | 2 | 176 mil. € | 5 | 5 | 7,0 | 4/2015 | 44 | 2/2032 (+4,9) | |||
20 | 44. - 45. | 2/2029 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 7,0 | 9/2009 | 45 | 2/2033 (+4,5) | |||
21 | 47. | 7/2029 | 14,0 km | 2 | 117 mil. € | 5 | 4 | 6,0 | 12/2014 | 47 | 7/2032 (+5,3) | |||
22 | 48. - 49. | 9/2029 | 9,8 km | 2 | 93 mil. € | 5 | 5 | 7,0 | 4/2015 | 48 | 9/2032 (+5,6) | |||
23 | 62. - 63. | 10/2032 | 8,5 km | 6 | 90 mil. € | 5 | 5 | 9,0 | 3/2016 | 62 | 10/2035 (+5,6) | |||
24 | 62. - 63. | 10/2032 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 9,0 | 3/2016 | 61 | 10/2035 (+5,9) | |||
25 | 71. - 78. | po 2040 | 42,1 km | 4 | 631 mil. € | 5 | 5 | 10,0 | 74 | po 2040 | ||||
26 | 71. - 78. | po 2040 | 29,2 km | 2 | 230 mil. € | 5 | 5 | 7,0 | 5/2016 | 76 | po 2040 (0,0) | |||
27 | 71. - 78. | po 2040 | 3,1 km | 4 | 60 mil. € | 5 | 5 | 5,0 | 6/2014 | 75 | po 2040 (0,0) | |||
28 | 71. - 78. | po 2040 | 32,8 km | 2 | 367 mil. € | 5 | 5 | 9,0 | 5/2016 | 78 | po 2040 (0,0) | |||
29 | 71. - 78. | po 2040 | 71,3 km | 2 | 553 mil. € | 5 | 5 | 9,0 | 5/2016 | 77 | po 2040 (0,0) | |||
398,5 km |
2 - 8 |
6 808 mil. € |
2,7 |
2,9 |
3 - 78 |
11/2015 - po 2040 |
11/2015 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku