plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||
26 úsekov |
264,3 km |
2 - 6 |
7 835 m |
4 911 mil. € |
2,2 |
2,0 |
6/2017 - po 2040 | ||||
1 | R3 | 8,7 km | 2 | 45 m | 94 mil. € | 4 | 2 | 8/2034 (+2,1) | |||
2 | R3 | 10,3 km | 2 | 300 m | 92 mil. € | 4 | 2 | po 2040 (0,0) | |||
3 | D3 | 4,3 km | 4 | 0 m | 269 mil. € | 4 | 2 | 12/2017 | |||
4 | D1 | 19,9 km | 6 | 321 mil. € | 3 | 2 | 9/2032 (+5,6) | ||||
5 | R3 | 10,9 km | 2 | 164 m | 129 mil. € | 3 | 2 | 8/2034 (+2,1) | |||
6 | R2 | 14,1 km | 2 | 60 m | 272 mil. € | 3 | 2 | 12/2029 (+5,4) | |||
7 | R3 | 5,0 km | 2 | 157 m | 63 mil. € | 3 | 2 | 11/2030 (+5,2) | |||
8 | D1 | 14,4 km | 4 | 1 660 m | 241 mil. € | 2 | 2 | 12/2019 | |||
9 | R2 | 6,2 km | 2 | 68 m | 105 mil. € | 2 | 2 | 3/2026 (+4,7) | |||
10 | D1 | 18,2 km | 4 | 408 m | 192 mil. € | 2 | 2 | 8/2036 (+7,9) | |||
11 | R3 | 4,9 km | 2 | 0 m | 77 mil. € | 2 | 2 | 10/2028 (+4,1) | |||
12 | R3 | 6,5 km | 2 | 428 m | 70 mil. € | 2 | 2 | 7/2026 (+2,7) | |||
13 | R4 | 4,0 km | 4 | 578 m | 105 mil. € | 2 | 2 | 8/2029 (+3,8) | |||
14 | R2 | 16,0 km | 4 | 496 m | 277 mil. € | 2 | 2 | 10/2028 (+3,2) | |||
15 | R2 | 13,5 km | 4 | 142 mil. € | 2 | 2 | 2021 (+1,1) | ||||
16 | R4 | 7,0 km | 2 | 227 m | 122 mil. € | 2 | 2 | 6/2030 (+3,7) | |||
17 | D3 | 12,3 km | 2 | 377 mil. € | 2 | 2 | 6/2017 | ||||
18 | R3 | 4,4 km | 2 | 135 m | 70 mil. € | 2 | 2 | 8/2022 (+2,2) | |||
19 | R2 | 8,3 km | 2 | 57 m | 169 mil. € | 2 | 2 | 8/2026 (+5,1) | |||
20 | R2 | 17,5 km | 4 | 228 m | 287 mil. € | 2 | 2 | 7/2034 (+10,0) | |||
21 | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | |||||
22 | D4 | 22,6 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | |||||
23 | D1 | 13,5 km | 4 | 240 m | 555 mil. € | 1 | 2 | 2024 (+4,0) | |||
24 | D3 | 4,0 km | 4 | 179 mil. € | 1 | 2 | 11/2030 (+6,4) | ||||
25 | D1 | 7,9 km | 4 | 1 513 m | 434 mil. € | 1 | 2 | 7/2021 (0,0) | |||
26 | D3 | 5,7 km | 4 | 1 071 m | 269 mil. € | 1 | 2 | 2021 (+0,5) | |||
26 úsekov |
264,3 km |
2 - 6 |
7 835 m |
4 911 mil. € |
2,2 |
2,0 |
6/2017 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku