plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||
26 úsekov |
264,3 km |
2 - 6 |
4 911 mil. € |
2,2 |
2,0 |
6/2017 - po 2040 | |||||
1 | R3 | 10,3 km | 2 | 92 mil. € | 947 - 1 015 | 4 | 2 | po 2040 (0,0) | |||
2 | D1 | 18,2 km | 4 | 192 mil. € | 441 - 647 | 2 | 2 | 8/2036 (+7,9) | |||
3 | R3 | 8,7 km | 2 | 94 mil. € | 562 | 4 | 2 | 8/2034 (+2,1) | |||
4 | R3 | 10,9 km | 2 | 129 mil. € | 410 - 1 220 | 3 | 2 | 8/2034 (+2,1) | |||
5 | R2 | 17,5 km | 4 | 287 mil. € | 1 311 - 1 980 | 2 | 2 | 7/2034 (+10,0) | |||
6 | D1 | 19,9 km | 6 | 321 mil. € | 3 137 - 3 460 | 3 | 2 | 9/2032 (+5,6) | |||
7 | D3 | 4,0 km | 4 | 179 mil. € | 2 660 | 1 | 2 | 11/2030 (+6,4) | |||
8 | R3 | 5,0 km | 2 | 63 mil. € | 711 - 822 | 3 | 2 | 11/2030 (+5,2) | |||
9 | R4 | 7,0 km | 2 | 122 mil. € | 1 103 - 1 149 | 2 | 2 | 6/2030 (+3,7) | |||
10 | R2 | 14,1 km | 2 | 272 mil. € | 456 - 489 | 3 | 2 | 12/2029 (+5,4) | |||
11 | R4 | 4,0 km | 4 | 105 mil. € | 1 056 | 2 | 2 | 8/2029 (+3,8) | |||
12 | R2 | 16,0 km | 4 | 277 mil. € | 1 040 - 1 450 | 2 | 2 | 10/2028 (+3,2) | |||
13 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 10/2028 (+4,1) | ||||
14 | R2 | 8,3 km | 2 | 169 mil. € | 692 - 710 | 2 | 2 | 8/2026 (+5,1) | |||
15 | R3 | 6,5 km | 2 | 70 mil. € | 742 - 818 | 2 | 2 | 7/2026 (+2,7) | |||
16 | R2 | 6,2 km | 2 | 105 mil. € | 704 | 2 | 2 | 3/2026 (+4,7) | |||
17 | D1 | 13,5 km | 4 | 555 mil. € | 639 - 3 702 | 1 | 2 | 2024 (+4,0) | |||
18 | R3 | 4,4 km | 2 | 70 mil. € | 577 - 783 | 2 | 2 | 8/2022 (+2,2) | |||
19 | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | |||||
20 | D4 | 22,6 km | 4 - 6 | 3 057 - 7 634 | 1 | 2 | 11/2021 (+0,4) | ||||
21 | R2 | 13,5 km | 4 | 142 mil. € | 1 039 - 1 131 | 2 | 2 | 2021 (+1,1) | |||
22 | D1 | 7,9 km | 4 | 434 mil. € | 1 186 - 1 322 | 1 | 2 | 7/2021 (0,0) | |||
23 | D3 | 5,7 km | 4 | 269 mil. € | 2 643 - 3 222 | 1 | 2 | 2021 (+0,5) | |||
24 | D1 | 14,4 km | 4 | 241 mil. € | 43 - 486 | 2 | 2 | 12/2019 | |||
25 | D3 | 4,3 km | 4 | 269 mil. € | 2 998 - 3 233 | 4 | 2 | 12/2017 | |||
26 | D3 | 12,3 km | 2 | 377 mil. € | 85 - 257 | 2 | 2 | 6/2017 | |||
26 úsekov |
264,3 km |
2 - 6 |
4 911 mil. € |
2,2 |
2,0 |
6/2017 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku