dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
264,3 km |
2 - 6 |
41 843 m |
4 911 mil. € |
2 541 - 93 344 | 2,2 |
2,0 |
6/2017 - 10/2021 | ||||||||||
1 | 7/2016 | D4 | 22,6 km | 4 - 6 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 32 336 - 93 344 | . . . | 1 679 - 8 658 | 3 640 - 7 825 | 1 | 2 | ||||||
2 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 42 774 - 54 519 | . . . | 2 765 - 3 271 | 3 862 - 4 344 | 3 | 2 | ||||
3 | 6/2014 | D3 | 4,3 km | 4 | 1 912 m | Brodno - dočasná | 269 mil. € | 28 413 - 37 927 | . . . | 1 886 - 2 202 | 4 356 - 4 665 | 4 | 2 | 12/2017 | |||
4 | 6/2014 | D1 | 13,5 km | 4 | 2 605 m | Lietavská Lúčka | 555 mil. € | 22 691 - 32 334 | 1 254 - 2 069 | 1 602 - 4 842 | 1 | 2 | |||||
5 | 59. | 7/2031 | R2 | 17,5 km | 4 | 2 458 m | Rákoš, Zvolenská Slatina | 287 mil. € | 12 819 - 29 988 | 940 - 1 697 | 1 901 - 3 009 | 2 | 2 | ||||
6 | 6/2017 | D1 | 7,9 km | 4 | 3 376 m | Prešov západ, Prešov juh | 434 mil. € | 19 072 - 21 988 | 1 228 - 1 350 | 1 935 - 2 218 | 1 | 2 | 10/2021 | ||||
7 | 12/2016 | D3 | 5,7 km | 4 | 3 435 m | Čadca Podzávoz, Čadca Bukov | 269 mil. € | 11 465 - 18 743 | 741 - 995 | 3 351 - 3 914 | 1 | 2 | 12/2020 (0,0) | ||||
8 | 31. | 11/2026 | D3 | 4,0 km | 4 | 624 m | 179 mil. € | 15 053 | 1 018 | 3 812 | 1 | 2 | |||||
9 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 2 045 m | Lipníky | 105 mil. € | 14 625 | 888 | 1 651 | 2 | 2 | ||||
10 | 3/2021 | R3 | 4,4 km | 2 | 1 703 m | Nižná,
Nižná - sever | 70 mil. € | 10 334 - 11 542 | 639 - 801 | 1 307 - 1 203 | 2 | 2 | |||||
11 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 1 929 m | Trenčianske Mitice | 277 mil. € | 9 654 - 12 079 | 692 - 940 | 1 577 - 2 085 | 2 | 2 | ||||
12 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 809 m | Šahy | 63 mil. € | 9 492 - 10 279 | 332 - 531 | 1 111 - 1 112 | 3 | 2 | ||||
13 | 8/2019 | R2 | 13,5 km | 4 | 1 631 m | Mýtna | 142 mil. € | 9 007 - 9 998 | 831 - 943 | 1 474 - 1 473 | 2 | 2 | |||||
14 | 12. | 7/2024 | R3 | 6,5 km | 2 | 1 892 m | privádzač Krupina | 70 mil. € | 6 706 - 9 733 | 393 - 539 | 1 175 - 1 262 | 2 | 2 | ||||
15 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 1 204 m | Široká, Jasenová, v mestskom variante tiež Kocmáľ (Mokraď) a Dolný Kubín stred | 129 mil. € | 5 586 - 10 745 | 561 - 714 | 791 - 1 514 | 3 | 2 | ||||
16 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 820 m | Hriadky, Pozdišovce | 192 mil. € | 6 207 - 8 525 | 404 - 665 | 911 - 840 | 2 | 2 | ||||
17 | 11/2016 | D1 | 14,4 km | 4 | 3 417 m | Budimír (Košice-Sever), Košické Olšany, Bidovce | 241 mil. € | 3 166 - 11 562 | 191 - 682 | 102 - 937 | 2 | 2 | 12/2019 (0,0) | ||||
18 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 223 m | Valaská Dubová, Likavka | 94 mil. € | 7 211 | 601 | 919 | 4 | 2 | ||||
19 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 1 095 m | Rožňava, Jablonov nad Turňou | 272 mil. € | 5 792 - 7 064 | 461 - 521 | 714 - 765 | 3 | 2 | ||||
20 | 13. | 8/2024 | R2 | 8,3 km | 2 | 457 m | Zacharovce, Bátka | 169 mil. € | 5 277 - 6 250 | 489 - 523 | 977 - 1 002 | 2 | 2 | ||||
21 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 395 m | 92 mil. € | 5 098 - 5 557 | 421 - 428 | 1 155 - 1 257 | 4 | 2 | |||||
22 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 411 m | 105 mil. € | 5 304 | 462 | 954 | 2 | 2 | |||||
23 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 1 948 m | Okrúhle | 122 mil. € | 3 407 - 3 769 | 201 - 240 | 1 298 - 1 289 | 2 | 2 | ||||
24 | 10/2013 | D3 | 12,3 km | 2 | 5 908 m | 377 mil. € | 2 541 - 3 501 | 194 - 270 | 216 - 455 | 2 | 2 | 6/2017 | |||||
25 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 1 544 m | Dlhá nad Oravou | 77 mil. € | 2 | 2 | |||||||
26 | 7/2016 | D4 | 4,4 km | 4 - 6 | Čierna voda, Rača | 1 | 2 | ||||||||||
264,3 km |
2 - 6 |
41 843 m |
4 911 mil. € |
2 541 - 93 344 | 2,2 |
2,0 |
6/2017 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku