dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||
264,3 km |
2 - 6 |
41 843 m |
4 911 mil. € |
2,2 |
2,0 |
6/2017 - po 2040 | |||||||
1 | 10/2013 | D3 | 12,3 km | 2 | 5 908 m | 377 mil. € | 2 | 2 | 6/2017 | ||||
2 | 6/2014 | D1 | 13,5 km | 4 | 2 605 m | 555 mil. € | 1 | 2 | 2024 (+4,0) | ||||
3 | 6/2014 | D3 | 4,3 km | 4 | 1 912 m | 269 mil. € | 4 | 2 | 12/2017 | ||||
4 | 7/2016 | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | ||||||
5 | 7/2016 | D4 | 22,6 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | ||||||
6 | 11/2016 | D1 | 14,4 km | 4 | 3 417 m | 241 mil. € | 2 | 2 | 12/2019 | ||||
7 | 12/2016 | D3 | 5,7 km | 4 | 3 435 m | 269 mil. € | 1 | 2 | 2021 (+0,5) | ||||
8 | 6/2017 | D1 | 7,9 km | 4 | 3 376 m | 434 mil. € | 1 | 2 | 7/2021 (0,0) | ||||
9 | 8/2019 | R2 | 13,5 km | 4 | 1 631 m | 142 mil. € | 2 | 2 | 0,0 | 2021 (+1,1) | |||
10 | 3/2021 | R3 | 4,4 km | 2 | 1 703 m | 70 mil. € | 2 | 2 | 0,1 | 8/2022 (+2,2) | |||
11 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 411 m | 105 mil. € | 2 | 2 | 2,5 | 3/2026 (+4,7) | ||
12 | 12. | 7/2024 | R3 | 6,5 km | 2 | 1 892 m | 70 mil. € | 2 | 2 | 2,8 | 7/2026 (+2,7) | ||
13 | 13. | 8/2024 | R2 | 8,3 km | 2 | 457 m | 169 mil. € | 2 | 2 | 2,8 | 8/2026 (+5,1) | ||
14 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 1 095 m | 272 mil. € | 3 | 2 | 3,2 | 12/2029 (+5,4) | ||
15 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 1 544 m | 77 mil. € | 2 | 2 | 4,0 | 10/2028 (+4,1) | ||
16 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 1 929 m | 277 mil. € | 2 | 2 | 4,1 | 10/2028 (+3,2) | ||
17 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 2 045 m | 105 mil. € | 2 | 2 | 4,9 | 8/2029 (+3,8) | ||
18 | 31. | 11/2026 | D3 | 4,0 km | 4 | 624 m | 179 mil. € | 1 | 2 | 5,1 | 11/2030 (+6,4) | ||
19 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 1 948 m | 122 mil. € | 2 | 2 | 5,7 | 6/2030 (+3,7) | ||
20 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 3 | 2 | 6,5 | 9/2032 (+5,6) | |||
21 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 809 m | 63 mil. € | 3 | 2 | 7,1 | 11/2030 (+5,2) | ||
22 | 59. | 7/2031 | R2 | 17,5 km | 4 | 2 458 m | 287 mil. € | 2 | 2 | 9,8 | 7/2034 (+10,0) | ||
23 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 223 m | 94 mil. € | 4 | 2 | 9,9 | 8/2034 (+2,1) | ||
24 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 1 204 m | 129 mil. € | 3 | 2 | 9,9 | 8/2034 (+2,1) | ||
25 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 820 m | 192 mil. € | 2 | 2 | 11,9 | 8/2036 (+7,9) | ||
26 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 395 m | 92 mil. € | 4 | 2 | >20 | po 2040 (0,0) | ||
264,3 km |
2 - 6 |
41 843 m |
4 911 mil. € |
2,2 |
2,0 |
6/2017 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku