plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||
26 úsekov |
254,3 km |
2 - 4 |
5 422 mil. € |
3,0 |
3,0 |
7/2020 - 8/2037 |
7. - 46. | |||||
1 | ![]() | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | 2,0 | 4/2026 (+3,7) | 27. | ||
2 | ![]() | D1 | 7,3 km | 4 | 321 mil. € | 3 | 3 | 7,0 | 9/2033 (+5,8) | |||
3 | ![]() | D1 | 12,6 km | 4 | 418 mil. € | 3 | 3 | 9,0 | 8/2036 (+7,9) | 11. | ||
4 | ![]() | R7 | 17,4 km | 4 | 2 | 3 | 7/2020 (+0,0) | |||||
5 | ![]() | R4 | 6,5 km | 2 | 116 mil. € | 2 | 3 | 5,0 | 6/2030 (+3,7) | 14. | ||
6 | ![]() | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 10,0 | 8/2037 (+5,9) | 7. | ||
7 | ![]() | D1 | 11,3 km | 4 | 517 mil. € | 2 | 3 | 2021 (+2,1) | ||||
8 | ![]() | R2 | 6,8 km | 4 | 171 mil. € | 3 | 3 | 1,0 | 7/2026 (+4,3) | |||
9 | ![]() | R4 | 8,0 km | 2 | 133 mil. € | 4 | 3 | 6,0 | 5/2033 (+6,1) | 44. | ||
10 | ![]() | R4 | 8,2 km | 2 | 94 mil. € | 3 | 3 | 4,0 | 6/2027 (+4,7) | 36. | ||
11 | ![]() | R3 | 14,0 km | 4 | 191 mil. € | 3 | 3 | 8,0 | 6/2034 (+7,0) | 7. | ||
12 | ![]() | R6 | 11,2 km | 2 | 182 mil. € | 4 | 3 | 8,0 | 7/2033 (+4,3) | 13. | ||
13 | ![]() | D1 | 15,8 km | 4 | 139 mil. € | 4 | 3 | 9,0 | 8/2036 (+7,7) | 9. | ||
14 | ![]() | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 7,0 | 9/2032 (+4,1) | 7. | ||
15 | ![]() | R3 | 8,3 km | 2 | 199 mil. € | 2 | 3 | 4,0 | 10/2028 (+4,1) | 17. | ||
16 | ![]() | D1 | 12,1 km | 4 | 162 mil. € | 3 | 3 | 9,0 | 8/2036 (+7,7) | 9. | ||
17 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 0,0 | 2023 (+2,0) | |||
18 | ![]() | R4 | 10,2 km | 4 | 299 mil. € | 1 | 3 | 1,0 | 1/2027 (+4,8) | |||
19 | ![]() | R4 | 7,5 km | 2 | 124 mil. € | 3 | 3 | 6,0 | 5/2033 (+6,1) | 21. | ||
20 | ![]() | R1 | 2,7 km | 4 | 155 mil. € | 4 | 3 | 4,0 | 6/2026 (+3,5) | 7. | ||
21 | ![]() | R1 | 4,6 km | 4 | 100 mil. € | 4 | 3 | 8,0 | 10/2028 (+3,5) | 7. | ||
22 | ![]() | R1 | 14,9 km | 4 | 785 mil. € | 3 | 3 | 7,0 | 2/2031 (+6,9) | 7. | ||
23 | ![]() | D1 | 15,5 km | 4 | 136 mil. € | 4 | 3 | 9,0 | 8/2036 (+7,7) | 29. | ||
24 | ![]() | R4 | 6,0 km | 2 | 101 mil. € | 4 | 3 | 6,0 | 5/2033 (+6,1) | 38. | ||
25 | ![]() | R4 | 7,9 km | 2 | 129 mil. € | 4 | 3 | 7,0 | 11/2031 (+4,8) | 46. | ||
26 | ![]() | R6 | 11,3 km | 2 | 222 mil. € | 4 | 3 | 8,0 | 7/2033 (+4,3) | 10. | ||
26 úsekov |
254,3 km |
2 - 4 |
5 422 mil. € |
3,0 |
3,0 |
7/2020 - 8/2037 |
7. - 46. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku