plánovaný
|
odhad NDS
|
stavebné práce
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||
26 úsekov |
254,3 km |
2 - 4 |
5 422 mil. € |
427,2 mil. € |
153,8 km |
3,0 |
3,0 |
7/2020 - 8/2037 | ||||
1 | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | 4/2026 (+3,7) | |||||
2 | D1 | 7,3 km | 4 | 321 mil. € | 7,3 km | 3 | 3 | 9/2033 (+5,8) | ||||
3 | D1 | 12,6 km | 4 | 418 mil. € | 14,3 km | 3 | 3 | 8/2036 (+7,9) | ||||
4 | R7 | 17,4 km | 4 | 18,4 km | 2 | 3 | 7/2020 (+0,0) | |||||
5 | R4 | 6,5 km | 2 | 116 mil. € | 7,9 km | 2 | 3 | 6/2030 (+3,7) | ||||
6 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | |||||
7 | D1 | 11,3 km | 4 | 517 mil. € | 427,2 mil. € | 15,5 km | 2 | 3 | 2021 (+2,1) | |||
8 | R2 | 6,8 km | 4 | 171 mil. € | 3 | 3 | 7/2026 (+4,3) | |||||
9 | R4 | 8,0 km | 2 | 133 mil. € | 8,9 km | 4 | 3 | 5/2033 (+6,1) | ||||
10 | R4 | 8,2 km | 2 | 94 mil. € | 7,9 km | 3 | 3 | 6/2027 (+4,7) | ||||
11 | R3 | 14,0 km | 4 | 191 mil. € | 3 | 3 | 6/2034 (+7,0) | |||||
12 | R6 | 11,2 km | 2 | 182 mil. € | 4 | 3 | 7/2033 (+4,3) | |||||
13 | D1 | 15,8 km | 4 | 139 mil. € | 17,5 km | 4 | 3 | 8/2036 (+7,7) | ||||
14 | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 9/2032 (+4,1) | |||||
15 | R3 | 8,3 km | 2 | 199 mil. € | 10,0 km | 2 | 3 | 10/2028 (+4,1) | ||||
16 | D1 | 12,1 km | 4 | 162 mil. € | 7,5 km | 3 | 3 | 8/2036 (+7,7) | ||||
17 | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 2023 (+2,0) | |||||
18 | R4 | 10,2 km | 4 | 299 mil. € | 1 | 3 | 1/2027 (+4,8) | |||||
19 | R4 | 7,5 km | 2 | 124 mil. € | 8,3 km | 3 | 3 | 5/2033 (+6,1) | ||||
20 | R1 | 2,7 km | 4 | 155 mil. € | 4 | 3 | 6/2026 (+3,5) | |||||
21 | R1 | 4,6 km | 4 | 100 mil. € | 4 | 3 | 10/2028 (+3,5) | |||||
22 | R1 | 14,9 km | 4 | 785 mil. € | 3 | 3 | 2/2031 (+6,9) | |||||
23 | D1 | 15,5 km | 4 | 136 mil. € | 16,0 km | 4 | 3 | 8/2036 (+7,7) | ||||
24 | R4 | 6,0 km | 2 | 101 mil. € | 6,3 km | 4 | 3 | 5/2033 (+6,1) | ||||
25 | R4 | 7,9 km | 2 | 129 mil. € | 8,0 km | 4 | 3 | 11/2031 (+4,8) | ||||
26 | R6 | 11,3 km | 2 | 222 mil. € | 4 | 3 | 7/2033 (+4,3) | |||||
26 úsekov |
254,3 km |
2 - 4 |
5 422 mil. € |
427,2 mil. € |
153,8 km |
3,0 |
3,0 |
7/2020 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku