✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||
26 úsekov |
254,3 km |
2 - 4 |
8 006 m |
5 422 mil. € |
1 698 - 50 895 | 3,0 |
3,0 |
7/2020 - 8/2037 | |||||
1 | 69. - 70. | 8/2034 | 14,0 km | 2 | 60 m | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | ||||
2 | 64. - 68. | 8/2033 | 12,6 km | 4 | 53 m | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 8/2036 (+7,9) | |||
3 | 64. - 68. | 8/2033 | 15,8 km | 4 | 213 m | 139 mil. € | 4 033 - 8 369 | 4 | 3 | 8/2036 (+7,7) | |||
4 | 64. - 68. | 8/2033 | 12,1 km | 4 | 154 m | 162 mil. € | 10 444 - 14 783 | 3 | 3 | 8/2036 (+7,7) | |||
5 | 64. - 68. | 8/2033 | 15,5 km | 4 | 303 m | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 8/2036 (+7,7) | |||
6 | 57. - 58. | 6/2031 | 14,0 km | 4 | 433 m | 191 mil. € | 14 233 - 18 874 | 3 | 3 | 6/2034 (+7,0) | |||
7 | 53. - 54. | 7/2030 | 11,2 km | 2 | 440 m | 182 mil. € | 7 234 | 4 | 3 | 7/2033 (+4,3) | |||
8 | 53. - 54. | 7/2030 | 11,3 km | 2 | 265 m | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | |||
9 | 50. - 52. | 5/2030 | 8,0 km | 2 | 86 m | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | |||
10 | 50. - 52. | 5/2030 | 7,5 km | 2 | 137 m | 124 mil. € | 3 769 - 3 897 | 3 | 3 | 5/2033 (+6,1) | |||
11 | 50. - 52. | 5/2030 | 6,0 km | 2 | 199 m | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | |||
12 | 48. - 49. | 9/2029 | 7,9 km | 2 | 110 m | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 9/2032 (+4,1) | |||
13 | 46. | 3/2029 | 7,3 km | 4 | 321 mil. € | 10 359 | 3 | 3 | 9/2033 (+5,8) | ||||
14 | 42. - 43. | 11/2028 | 7,9 km | 2 | 164 m | 129 mil. € | 2 552 - 2 737 | 4 | 3 | 11/2031 (+4,8) | |||
15 | 37. - 38. | 2/2028 | 14,9 km | 4 | 446 m | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 2/2031 (+6,9) | |||
16 | 34. - 36. | 6/2027 | 6,5 km | 2 | 101 m | 116 mil. € | 6 651 - 9 113 | 2 | 3 | 6/2030 (+3,7) | |||
17 | 30. | 10/2026 | 4,6 km | 4 | 1 757 m | 100 mil. € | 11 611 | 4 | 3 | 10/2028 (+3,5) | |||
18 | 20. - 23. | 10/2025 | 8,3 km | 2 | 192 m | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 10/2028 (+4,1) | |||
19 | 19. | 6/2025 | 8,2 km | 2 | 34 m | 94 mil. € | 4 001 | 3 | 3 | 6/2027 (+4,7) | |||
20 | 11. | 6/2024 | 2,7 km | 4 | 131 m | 155 mil. € | 16 268 | 4 | 3 | 6/2026 (+3,5) | |||
21 | 6. | 7/2023 | 6,8 km | 4 | 1 169 m | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 7/2026 (+4,3) | |||
22 | 5. | 4/2023 | 8,1 km | 4 | 1 018 m | 173 mil. € | 12 387 - 17 316 | 2 | 3 | 4/2026 (+3,7) | |||
23 | 4. | 9/2022 | 10,2 km | 4 | 206 m | 299 mil. € | 22 341 - 30 731 | 1 | 3 | 1/2027 (+4,8) | |||
24 | 7/2019 | 4,3 km | 4 | 337 m | 179 mil. € | 15 837 - 18 098 | 1 | 3 | 2023 (+2,0) | ||||
25 | 7/2016 | 17,4 km | 4 | 8 544 - 13 236 | 2 | 3 | 7/2020 (+0,0) | ||||||
26 | 1/2014 | 11,3 km | 4 | 0 m | 517 mil. € | 23 579 - 28 413 | 2 | 3 | 2021 (+2,1) | ||||
26 úsekov |
254,3 km |
2 - 4 |
8 006 m |
5 422 mil. € |
1 698 - 50 895 | 3,0 |
3,0 |
7/2020 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku