dátum |
plánovaný
|
odhad NDS
|
pozemky
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
26 úsekov |
254,3 km |
2 - 4 |
5 422 mil. € |
287,5 mil. € |
3,0 |
3,0 |
12/2017 - 12/2033 |
7/2020 - 1/2021 | |||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | R 22,5/100 | 173 mil. € | 16,6 mil. € | 2 | 3 | 8/2022 | ||||
2 | 46. | 3/2029 | D1 | 7,3 km | 4 | 26,5/100 | 321 mil. € | 0,5 mil. € | 3 | 3 | 7/2028 | ||||
3 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | D 26,5/120
(100) | 418 mil. € | 7,0 mil. € | 3 | 3 | 8/2032 | ||||
4 | 7/2016 | R7 | 17,4 km | 4 | R 24,5/120 | 30,8 mil. € | 2 | 3 | 7/2020 (0,0) | ||||||
5 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 116 mil. € | 12,6 mil. € | 2 | 3 | 6/2026 | ||||
6 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 305 mil. € | 15,0 mil. € | 3 | 3 | 12/2033 | ||||
7 | 1/2014 | D1 | 11,3 km | 4 | D 26,5/100 | 517 mil. € | 14,7 mil. € | 2 | 3 | 1/2021 (0,0) | |||||
8 | 6. | 7/2023 | R2 | 6,8 km | 4 | R 24,5/100 | 171 mil. € | 35,4 mil. € | 3 | 3 | 7/2022 | ||||
9 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 133 mil. € | 6,0 mil. € | 4 | 3 | 5/2029 | ||||
10 | 19. | 6/2025 | R4 | 8,2 km | 2 | R 24,5/100, plánované v 1/2-profile | 94 mil. € | 2,1 mil. € | 3 | 3 | 6/2024 | ||||
11 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | R 24,5/120 (100) | 191 mil. € | 19,0 mil. € | 3 | 3 | 10/2030 | ||||
12 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R 11,5/100 (80) | 182 mil. € | 10,0 mil. € | 4 | 3 | 11/2029 | ||||
13 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | D 26,5/120
(100) | 139 mil. € | 5,0 mil. € | 4 | 3 | 8/2032 | ||||
14 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 71 mil. € | 8,9 mil. € | 4 | 3 | 1/2029 | ||||
15 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | 199 mil. € | 7,1 mil. € | 2 | 3 | 2/2025 | ||||
16 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | D 26,5/120
(100) | 162 mil. € | 7,0 mil. € | 3 | 3 | 8/2032 | ||||
17 | 7/2019 | R4 | 4,3 km | 4 | R 24,5/100 | 179 mil. € | 17,1 mil. € | 1 | 3 | 12/2017 | |||||
18 | 4. | 9/2022 | R4 | 10,2 km | 4 | R 24,5/100 | 299 mil. € | 22,4 mil. € | 1 | 3 | 10/2021 | ||||
19 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 124 mil. € | 4,8 mil. € | 3 | 3 | 5/2029 | ||||
20 | 11. | 6/2024 | R1 | 2,7 km | 4 | R 24,5/80 | 155 mil. € | 8,3 mil. € | 4 | 3 | 10/2023 | ||||
21 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | 100 mil. € | 2,8 mil. € | 4 | 3 | 2/2026 | ||||
22 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | R 24,5/80 | 785 mil. € | 7,9 mil. € | 3 | 3 | 6/2027 | ||||
23 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | D 26,5/120
(100) | 136 mil. € | 5,0 mil. € | 4 | 3 | 8/2032 | ||||
24 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 101 mil. € | 6,1 mil. € | 4 | 3 | 5/2029 | ||||
25 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | R 24,5/100, plánované v 1/2-profile | 129 mil. € | 4,4 mil. € | 4 | 3 | 11/2027 | ||||
26 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R 11,5/100 (80) | 222 mil. € | 11,0 mil. € | 4 | 3 | 11/2029 | ||||
26 úsekov |
254,3 km |
2 - 4 |
5 422 mil. € |
287,5 mil. € |
3,0 |
3,0 |
12/2017 - 12/2033 |
7/2020 - 1/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku