dátum |
plánovaný
|
odhad NDS
|
- predĺženie
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
574,2 km |
2 - 6 |
9 515 mil. € |
10,5 km |
3,6 |
3,7 |
7/2020 - 1/2021 | ||||||||
1 | 1/2014 | D1 | 11,3 km | 4 | 517 mil. € | 4,2 km | Trasu od Bratislavy po križovatku Rondel v centre Žiliny tento úsek D1 predĺži o vyše 3 km a zrýchli sotva o 1 minútu. Zo zdrojovej a cieľovej dopravy Žiliny zrýchli citeľne iba cesty začínajúce alebo končiace na juhu Žiliny. | 2 | 3 | 1/2021 (0,0) | ||||
2 | 7/2016 | R7 | 17,4 km | 4 | 1,0 km | 2 | 3 | 7/2020 (0,0) | ||||||
3 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 100 % | ||||||
4 | 4. | 9/2022 | R4 | 10,2 km | 4 | 299 mil. € | 1 | 3 | 98 % | |||||
5 | 5. | 4/2023 | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | 7 % | |||||
6 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 3 | 3 | 99 % | |||||
7 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 191 mil. € | 0,7 km | 4 | 5 | 0 % | ||||
8 | 10. | 4/2024 | D1 | 3,8 km | 2 | 57 mil. € | 3 | 5 | 30 %, pozastavené | |||||
9 | 11. | 6/2024 | R1 | 2,7 km | 4 | 155 mil. € | 4 | 3 | 0 % | |||||
10 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | 161 mil. € | 4 | 5 | 0 % | |||||
11 | 19. | 6/2025 | R4 | 8,2 km | 2 | 94 mil. € | -0,3 km | 3 | 3 | 0 % | ||||
12 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 2,3 km | 2 | 3 | 0 % | ||||
13 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 4 | 3 | 0 % | |||||
14 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 224 mil. € | -1,6 km | 3 | 5 | 0 % | ||||
15 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 116 mil. € | 1,5 km | 2 | 3 | 0 % | ||||
16 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 785 mil. € | 3 | 3 | 0 % | |||||
17 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 129 mil. € | -0,3 km | 4 | 3 | 0 % | ||||
18 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 0,2 km | 5 | 5 | 0 % | ||||
19 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 0 % | |||||
20 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 0,0 km | 3 | 3 | 0 % | ||||
21 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 0,0 km | 5 | 5 | 0 % | ||||
22 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 0 % | |||||
23 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 0,4 km | 4 | 3 | 0 % | ||||
24 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 1,3 km | 3 | 3 | 0 % | ||||
25 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 0,3 km | 4 | 3 | 0 % | ||||
26 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 4 | 3 | 0 % | |||||
27 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 4 | 3 | 0 % | |||||
28 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 3 | 5 | 0 % | |||||
29 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 3 | 3 | 0 % | |||||
30 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 5 | 5 | 0 % | |||||
31 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 0 % | |||||
32 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 418 mil. € | 1,7 km | 3 | 3 | 0 % | ||||
33 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 2,8 km | 4 | 3 | 0 % | ||||
34 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 162 mil. € | -4,3 km | 3 | 3 | 0 % | ||||
35 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 136 mil. € | 0,5 km | 4 | 3 | 0 % | ||||
36 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 0 % | |||||
37 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | 631 mil. € | 5 | 5 | 0 % | |||||
38 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | 230 mil. € | 5 | 5 | 0 % | |||||
39 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 | 5 | 0 % | |||||
40 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | 367 mil. € | 5 | 5 | 0 % | |||||
41 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | 553 mil. € | 5 | 5 | 0 % | |||||
574,2 km |
2 - 6 |
9 515 mil. € |
10,5 km |
3,6 |
3,7 |
7/2020 - 1/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku