dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
283,3 km |
2 - 4 |
12 |
4 893 mil. € |
3,5 |
4,0 |
6/2018 - po 2040 |
|||||||||
1 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 8/2007 | 12/2010 | 5/2026 | |||
2 | 69. - 70. | 8/2034 | ![]() | R2 | 49,0 km | 2 | 662 mil. € | 4 | 4 | 12/1998 | 10/2004 | 12/2033 | |||
3 | 71. - 78. | po 2040 | ![]() | R3 | 58,5 km | 2 | 3 | 611 mil. € | 4 | 4 | 6/2008 | 11/2018 | po 2040 | ||
4 | 55. - 56. | 5/2031 | ![]() | R1 | 11,5 km | 4 | 1 | 406 mil. € | 4 | 4 | 9/2009 | 4/2010 | 9/2030 | ||
5 | 55. - 56. | 5/2031 | ![]() | R1 | 9,5 km | 4 | 339 mil. € | 4 | 4 | 9/2009 | 4/2010 | 9/2030 | |||
6 | 25. | 1/2026 | ![]() | D3 | 10,8 km | 4 | 2 | 309 mil. € | 2 | 4 | 7/1996 | 12/1997 | 5/2025 | ||
7 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 3 | 4 | 11/2003 | 11/2004 | 6/2018 | ||||
8 | 41. | 9/2028 | ![]() | R2 | 11,5 km | 2 | 1 | 235 mil. € | 2 | 4 | 12/1998 | 10/2004 | 1/2028 | ||
9 | 14. - 15. | 10/2024 | ![]() | R7 | 23,5 km | 2 | 1 | 227 mil. € | 4 | 4 | 10/2005 | 12/2011 | 2/2024 | ||
10 | 26. | 4/2026 | ![]() | R2 | 20,7 km | 2 | 1 | 211 mil. € | 4 | 4 | 11/2004 | 10/2006 | 8/2025 | ||
11 | 14. - 15. | 10/2024 | ![]() | R7 | 14,3 km | 2 | 1 | 172 mil. € | 4 | 4 | 10/2005 | 12/2011 | 2/2024 | ||
12 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 3 | 4 | 12/1998 | 11/2003 | 4/2025 | |||
13 | 28. - 29. | 8/2026 | ![]() | R2 | 10,6 km | 2 | 125 mil. € | 4 | 4 | 10/2000 | 11/2004 | 12/2025 | |||
14 | 47. | 7/2029 | ![]() | R2 | 14,0 km | 2 | 1 | 117 mil. € | 5 | 4 | 5/2008 | 6/2016 | 7/2028 | ||
15 | 39. - 40. | 3/2028 | ![]() | R2 | 9,6 km | 2 | 112 mil. € | 2 | 4 | 12/1998 | 10/2004 | 7/2027 | |||
16 | 37. - 38. | 2/2028 | ![]() | R2 | 7,8 km | 2 | 73 mil. € | 5 | 4 | 12/2007 | 9/2009 | 2/2027 | |||
17 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 1 | 59 mil. € | 3 | 4 | 12/1998 | 11/2003 | 2/2025 | ||
18 | 71. - 78. | po 2040 | ![]() | R5 | 1,7 km | 2 | 54 mil. € | 3 | 4 | 2/2007 | 10/2009 | ||||
283,3 km |
2 - 4 |
12 |
4 893 mil. € |
3,5 |
4,0 |
6/2018 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku