dátum |
plánovaný
|
odhad NDS
|
1 - optimálne,
5 - neprimerané |
prebratie
|
+ posun v rokoch
za posledné cca 4 roky | |||||||||
18 úsekov |
283,3 km |
2 - 4 |
4 893 mil. € |
3 247 - 14 648 | 4,0 |
7/2024 - po 2040 |
0.1 - 0.82 | ||||||||
1 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 4 | 9/2009 | 6/2033 (+3,3) | nedostupný údaj | ||||
2 | 39. - 40. | 3/2028 | ![]() | R2 | 9,6 km | 2 | 112 mil. € | 8 634 - 11 116 | 4 | 9/2014 | 3/2031 (+5,9) | 0,22 | |||
3 | 14. - 15. | 10/2024 | ![]() | R7 | 23,5 km | 2 | 227 mil. € | 4 | 11/2014 | 4/2029 (+4,1) | 0,59 | ||||
4 | 37. - 38. | 2/2028 | ![]() | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 4 | 4/2015 | 2/2031 (+4,1) | -0,04 | |||
5 | 55. - 56. | 5/2031 | ![]() | R1 | 11,5 km | 4 | 406 mil. € | 7 784 | 4 | 8/2015 | 5/2033 (+10,2) | nedostupný údaj | |||
6 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 8 780 - 11 203 | 4 | 7/2014 | 2024 (+2,8) | |||||
7 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 4 | 9/2014 | 12/2028 (+4,3) | 0,10 | |||
8 | 25. | 1/2026 | ![]() | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 4 | 6/2014 | 1/2029 (+3,0) | 0,43 | |||
9 | 55. - 56. | 5/2031 | ![]() | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 4 | 8/2015 | 5/2033 (+10,2) | nedostupný údaj | |||
10 | 26. | 4/2026 | ![]() | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 7/2014 | 4/2028 (+4,8) | 0,32 | |||
11 | 69. - 70. | 8/2034 | ![]() | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 2/2016 | 8/2037 (+5,9) | nedostupný údaj | |||
12 | 28. - 29. | 8/2026 | ![]() | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 4 | 6/2014 | 8/2028 (+5,1) | 0,18 | |||
13 | 41. | 9/2028 | ![]() | R2 | 11,5 km | 2 | 235 mil. € | 7 793 | 4 | 9/2014 | 9/2031 (+5,4) | 0,54 | |||
14 | 71. - 78. | po 2040 | ![]() | R5 | 1,7 km | 2 | 54 mil. € | 7 972 | 4 | 3/2025 (0,0) | 0,82 | ||||
15 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 4 | 9/2014 | 10/2028 (+4,2) | 0,65 | |||
16 | 47. | 7/2029 | ![]() | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 4 | 12/2014 | 7/2032 (+5,3) | 0,33 | |||
17 | 14. - 15. | 10/2024 | ![]() | R7 | 14,3 km | 2 | 172 mil. € | 4 | 11/2014 | 4/2029 (+4,1) | 0,59 | ||||
18 | 71. - 78. | po 2040 | ![]() | R3 | 58,5 km | 2 | 611 mil. € | 3 247 - 11 434 | 4 | 5/2015 | po 2040 (+13,9) | nedostupný údaj | |||
18 úsekov |
283,3 km |
2 - 4 |
4 893 mil. € |
3 247 - 14 648 | 4,0 |
7/2024 - po 2040 |
0.1 - 0.82 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku