dátum |
plánovaný
|
odhad NDS
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
603,2 km |
2 - 6 |
20 |
8 986 mil. € |
1 065 - 32 968 | 3,9 |
4,5 |
|||||||||
1 | 3/2020 | R2 | 9,1 km | 4 | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | 267 mil. € | 8 780 - 11 203 | 348 - 358 | 3 | 4 | |||||
2 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 191 mil. € | 6 428 - 9 084 | 189 - 255 | 4 | 5 | ||||
3 | 10. | 4/2024 | D1 | 3,8 km | 2 | R 11,5/80 | 57 mil. € | 10 312 | 231 | 3 | 5 | ||||
4 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | 1 | 227 mil. € | 4 | 4 | |||||
5 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | 1 | 172 mil. € | 4 | 4 | |||||
6 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | 161 mil. € | 6 403 - 9 478 | 248 - 279 | 4 | 5 | ||||
7 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 1 | 59 mil. € | 12 862 | 498 | 3 | 4 | |||
8 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 143 mil. € | 12 157 | 494 | 3 | 4 | ||||
9 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | 2 | 309 mil. € | 14 176 - 14 186 | 381 - 551 | 2 | 4 | |||
10 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 | 211 mil. € | 6 969 - 10 726 | 280 - 373 | 4 | 4 | |||
11 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | 125 mil. € | 6 412 - 8 112 | 193 - 261 | 4 | 4 | ||||
12 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | ||||||
13 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 224 mil. € | 10 140 - 11 010 | 299 - 336 | 3 | 5 | ||||
14 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 73 mil. € | 5 587 | 178 | 5 | 4 | ||||
15 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 112 mil. € | 8 634 - 11 116 | 240 - 422 | 2 | 4 | ||||
16 | 41. | 9/2028 | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 | 235 mil. € | 7 793 | 393 | 2 | 4 | |||
17 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 | 176 mil. € | 5 189 - 6 389 | 153 - 173 | 5 | 5 | |||
18 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | ||||||
19 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 | 117 mil. € | 5 809 - 8 826 | 226 - 259 | 5 | 4 | |||
20 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 6 452 - 10 032 | 212 - 272 | 5 | 5 | ||||
21 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | R 24,5/80 | 1 | 406 mil. € | 7 784 | 204 | 4 | 4 | |||
22 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | R 24,5/80 | 339 mil. € | 9 704 - 13 715 | 256 - 340 | 4 | 4 | ||||
23 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 4 151 - 11 477 | 149 - 407 | 3 | 5 | ||||
24 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | D 33,5/120 | 1 | 90 mil. € | 32 968 | . . . | 1 232 | 5 | 5 | ||
25 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | D 33,5/120 | 107 mil. € | 5 | 5 | ||||||
26 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 662 mil. € | 5 762 - 14 648 | 172 - 328 | 4 | 4 | ||||
27 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | R 24,5/120 | 631 mil. € | 5 713 - 13 545 | 129 - 338 | 5 | 5 | ||||
28 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | R 11,5/120 | 2 | 230 mil. € | 2 156 - 6 890 | 90 - 156 | 5 | 5 | |||
29 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | D 26,5/100 | 60 mil. € | 5 420 - 8 693 | 150 - 245 | 5 | 5 | ||||
30 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | R 11,5/70 | 54 mil. € | 7 972 | 246 | 3 | 4 | ||||
31 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | R 11,5/120 | 367 mil. € | 2 228 - 6 331 | 45 - 173 | 5 | 5 | ||||
32 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 3 | 611 mil. € | 3 247 - 11 434 | 62 - 372 | 4 | 4 | |||
33 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | R 11,5/120 | 4 | 553 mil. € | 1 065 - 4 239 | 39 - 162 | 5 | 5 | |||
603,2 km |
2 - 6 |
20 |
8 986 mil. € |
1 065 - 32 968 | 3,9 |
4,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku