dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
|
odhad INEKO
|
+ posun v rokoch
za posledné cca 4 roky | ||||||||
15 úsekov |
319,9 km |
2 - 6 |
4 093 mil. € |
4,5 |
5,0 |
4/2027 - po 2040 |
||||||||||
1 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 191 mil. € | 4 | 5 | 11/2014 | 9/2028 (+3,5) | |||||
2 | 10. | 4/2024 | D1 | 3,8 km | 2 | R 11,5/80 | 57 mil. € | 3 | 5 | 4/2027 (+4,1) | ||||||
3 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | 161 mil. € | 4 | 5 | 11/2014 | 5/2029 (+3,5) | |||||
4 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 224 mil. € | 3 | 5 | 12/2014 | 12/2029 (+2,8) | |||||
5 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 176 mil. € | 5 | 5 | 4/2015 | 2/2032 (+4,9) | |||||
6 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | 9/2009 | 2/2033 (+4,5) | |||||
7 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 5 | 5 | 4/2015 | 9/2032 (+5,6) | |||||
8 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 3 | 5 | 6/2036 (+2,3) | ||||||
9 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | D 33,5/120 | 90 mil. € | 5 | 5 | 3/2016 | 10/2035 (+5,6) | |||||
10 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | D 33,5/120 | 107 mil. € | 5 | 5 | 3/2016 | 10/2035 (+5,9) | |||||
11 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | R 24,5/120 | 631 mil. € | 5 | 5 | po 2040 | ||||||
12 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | R 11,5/120 | 230 mil. € | 5 | 5 | 5/2016 | po 2040 (0,0) | |||||
13 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | D 26,5/100 | 60 mil. € | 5 | 5 | 6/2014 | po 2040 (0,0) | |||||
14 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | R 11,5/120 | 367 mil. € | 5 | 5 | 5/2016 | po 2040 (0,0) | |||||
15 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | R 11,5/120 | 553 mil. € | 5 | 5 | 5/2016 | po 2040 (0,0) | |||||
15 úsekov |
319,9 km |
2 - 6 |
4 093 mil. € |
4,5 |
5,0 |
4/2027 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku