dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
44 úsekov |
460,2 km |
2 - 8 |
10 379 mil. € |
2 552 - 93 344 | 2,3 |
2,8 |
7/2020 - 10/2021 | ||||||||||
1 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D 33,5/120 | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | 12/2009 | ||||
2 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | D 41/120 | Senec | 234 mil. € | 62 652 | . . . | 2 | 1 | 12/2009 | ||||
3 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | 12/2010 | |||||||
4 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | Dlhá nad Oravou | 77 mil. € | 2 | 2 | 8/2006 | ||||||
5 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | Nováky - západ | 112 mil. € | 8 634 - 11 116 | 2 | 4 | 10/2004 | |||||
6 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | Zemné | 227 mil. € | 4 | 4 | 12/2011 | ||||||
7 | 7/2016 | R7 | 17,4 km | 4 | R 24,5/120 | Šamorín, Holice | 8 544 - 13 236 | 2 | 3 | 7/2020 (0,0) | |||||||
8 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | R 24,5/100, plánované v 1/2-profile | Kuková | 116 mil. € | 6 651 - 9 113 | 2 | 3 | ||||||
9 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | Holice s I/63, D. Streda s III/06325 | 191 mil. € | 6 428 - 9 084 | 4 | 5 | 12/2011 | |||||
10 | 1/2014 | D1 | 11,3 km | 4 | D 26,5/100 | 517 mil. € | 23 579 - 28 413 | 2 | 3 | 1/2021 (0,0) | |||||||
11 | 12/2013 | D1 | 14,9 km | 4 | D 26,5/100 | Hubová, Likavka, Ivachnová | 341 mil. € | 12 491 - 24 900 | 1 | 1 | |||||||
12 | 7/2016 | D4 | 4,4 km | 4 - 6 | D 33,5/120, D 26,5/120 | Čierna voda, Rača | 1 | 2 | |||||||||
13 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | Jablonov n.Turňou | 73 mil. € | 5 587 | 5 | 4 | 9/2009 | |||||
14 | 7/2016 | D4 | 22,6 km | 4 - 6 | D 33,5/120, D 26,5/120 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 32 336 - 93 344 | . . . | 1 | 2 | |||||||
15 | 7/2016 | R7 | 8,4 km | 4 | R 31,5/120 | Dunajská Lužná | 13 102 - 19 993 | 1 | 1 | 7/2020 (0,0) | |||||||
16 | 3/2020 | R2 | 9,1 km | 4 | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | Kriváň | 267 mil. € | 8 780 - 11 203 | 3 | 4 | 11/2004 | ||||||
17 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | Trenčín juh, Trenčianska Turná | 143 mil. € | 12 157 | 3 | 4 | 11/2003 | |||||
18 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | Krásno nad Kysucou | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 12/1997 | |||||
19 | 6/2014 | D1 | 13,5 km | 4 | D 26,5/100 | Lietavská Lúčka | 555 mil. € | 22 691 - 32 334 | 1 | 2 | |||||||
20 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | R 24,5/100 | Lipníky | 105 mil. € | 14 625 | 2 | 2 | ||||||
21 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 10/2006 | ||||||
22 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | Mliečany s II/507, Dolný Bar | 161 mil. € | 6 403 - 9 478 | 4 | 5 | 7/2018 | |||||
23 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | Trenčianske Mitice | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 11/2003 | |||||
24 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Moldava nad Bodvou, Šaca | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 6/2016 | |||||
25 | 8/2019 | R2 | 13,5 km | 4 | R 24,5/100 | Mýtna | 142 mil. € | 9 007 - 9 998 | 2 | 2 | 11/2004 | ||||||
26 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | Podbiel | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 8/2006 | |||||
27 | 31. | 11/2026 | D3 | 4,0 km | 4 | D 24,5/80 | 179 mil. € | 15 053 | 1 | 2 | 12/1997 | ||||||
28 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | Rimavská Sobota | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 11/2004 | |||||
29 | 41. | 9/2028 | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 7 793 | 2 | 4 | 10/2004 | ||||||
30 | 7/2019 | R4 | 4,3 km | 4 | R 24,5/100 | Prešov - sever | 179 mil. € | 15 837 - 18 098 | 1 | 3 | 5/2004 | ||||||
31 | 6/2017 | D1 | 7,9 km | 4 | D 26,5/100 | Prešov západ, Prešov juh | 434 mil. € | 19 072 - 21 988 | 1 | 2 | 2/2001 | 10/2021 | |||||
32 | 7/2016 | R7 | 6,4 km | 4 - 6 | R 31,5/120 | Prievoz | 27 633 - 44 493 | . . . | 1 | 1 | 10/2021 | ||||||
33 | 12/2017 | D1 | 2,6 km | 4 | R 22,5/80 | 39 mil. € | 14 624 | 1 | 1 | 1/2021 (0,0) | |||||||
34 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | R 24,5/100, plánované v 1/2-profile | Okrúhle | 122 mil. € | 3 407 - 3 769 | 2 | 2 | ||||||
35 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | Rožňava, Jablonov nad Turňou | 272 mil. € | 5 792 - 7 064 | 3 | 2 | 9/2009 | |||||
36 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | križovatka D1 | 100 mil. € | 11 611 | 4 | 3 | 4/2010 | |||||
37 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | R 24,5/80 | Slovenská Ľupča, Korytnica | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 4/2010 | |||||
38 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 12 862 | 3 | 4 | 11/2003 | ||||||
39 | 7. | 2/2024 | D1 | 13,5 km | 4 | D 26,5/100 | Turany 2, Hubová | 1 235 mil. € | 13 676 - 21 949 | 1 | 1 | ||||||
40 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | Nové Zámky | 172 mil. € | 4 | 4 | 12/2011 | ||||||
41 | 12/2016 | D3 | 5,7 km | 4 | D 24,5/80 | Čadca Podzávoz, Čadca Bukov | 269 mil. € | 11 465 - 18 743 | 1 | 2 | 12/2020 (0,0) | ||||||
42 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Šahy | 63 mil. € | 9 492 - 10 279 | 3 | 2 | 11/2018 | |||||
43 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | R 24,5/100, plánované v 1/2-profile | Hunkovce, Vyšný Komárnik | 129 mil. € | 2 552 - 2 737 | 4 | 3 | 4/2016 | |||||
44 | 27. | 5/2026 | D3 | 11,2 km | 4 | D 24,5/80 | Brodno, Kysucké Nové Mesto | 410 mil. € | 13 886 - 21 743 | 1 | 1 | 7/1997 | |||||
44 úsekov |
460,2 km |
2 - 8 |
10 379 mil. € |
2 552 - 93 344 | 2,3 |
2,8 |
7/2020 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku