dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
odhad INEKO
| ||||||||
346,3 km |
2 - 8 |
32 243 m |
6 138 mil. € |
77,3 min. |
2,7 |
2,8 |
11/2022 - 3/2024 |
|||||||
1 | 12/2013 | ![]() | D1 | 14,9 km | 4 | 4 388 m | 341 mil. € | 12,4 min. | 1 | 1 | 12/2023 | |||
2 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 2 605 m | 555 mil. € | 9,9 min. | 1 | 2 | 2/2024 | |||
3 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 1 221 m | 179 mil. € | 1 | 3 | 3/2023 | ||||
4 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 1 631 m | 142 mil. € | 5,0 min. | 2 | 2 | 11/2022 | |||
5 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 2 765 m | 267 mil. € | 2,6 min. | 3 | 4 | 3/2024 | |||
6 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 1 703 m | 70 mil. € | 3,6 min. | 2 | 2 | 6/2023 | |||
7 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 4 | 1 401 m | 202 mil. € | 2 | 1 | ||||
8 | 3. | 3/2022 | ![]() | D1 | 3,5 km | 8 | 1 352 m | 149 mil. € | 1 | 1 | ||||
9 | 4. | 9/2022 | ![]() | R4 | 10,2 km | 4 | 1 638 m | 299 mil. € | 1 | 3 | ||||
10 | 57. - 58. | 6/2031 | ![]() | R8 | 54,9 km | 4 | 1 020 mil. € | 3 | 5 | |||||
11 | 57. - 58. | 6/2031 | ![]() | R3 | 14,0 km | 4 | 1 456 m | 191 mil. € | 3 | 3 | ||||
12 | 59. | 7/2031 | ![]() | R2 | 17,5 km | 4 | 2 458 m | 287 mil. € | 6,3 min. | 2 | 2 | |||
13 | 60. - 61. | 8/2031 | ![]() | R3 | 8,7 km | 2 | 223 m | 94 mil. € | 1,4 min. | 4 | 2 | |||
14 | 60. - 61. | 8/2031 | ![]() | R3 | 10,9 km | 2 | 1 204 m | 129 mil. € | 3,8 min. | 3 | 2 | |||
15 | 62. - 63. | 10/2032 | ![]() | D2 | 8,5 km | 6 | 90 mil. € | 5 | 5 | |||||
16 | 62. - 63. | 10/2032 | ![]() | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | |||||
17 | 64. - 68. | 8/2033 | ![]() | D1 | 12,6 km | 4 | 218 m | 418 mil. € | 5,5 min. | 3 | 3 | |||
18 | 64. - 68. | 8/2033 | ![]() | D1 | 18,2 km | 4 | 820 m | 192 mil. € | 8,3 min. | 2 | 2 | |||
19 | 64. - 68. | 8/2033 | ![]() | D1 | 15,8 km | 4 | 393 m | 139 mil. € | 8,9 min. | 4 | 3 | |||
20 | 64. - 68. | 8/2033 | ![]() | D1 | 12,1 km | 4 | 537 m | 162 mil. € | 1,9 min. | 3 | 3 | |||
21 | 64. - 68. | 8/2033 | ![]() | D1 | 15,5 km | 4 | 646 m | 136 mil. € | 7,6 min. | 4 | 3 | |||
22 | 69. - 70. | 8/2034 | ![]() | R3 | 14,0 km | 2 | 2 701 m | 305 mil. € | 3 | 3 | ||||
23 | 69. - 70. | 8/2034 | ![]() | R2 | 49,0 km | 2 | 2 882 m | 662 mil. € | 4 | 4 | ||||
346,3 km |
2 - 8 |
32 243 m |
6 138 mil. € |
77,3 min. |
2,7 |
2,8 |
11/2022 - 3/2024 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku