dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||||
1 | 12/2013 | D1 | 14,9 km | 4 | 341 mil. € | 12 491 - 24 900 | 89 - 432 | 1 | 1 | 4/2009 | 12/2013 | |||||||
2 | 6/2014 | D1 | 13,5 km | 4 | 555 mil. € | 22 691 - 32 334 | 133 - 458 | 1 | 2 | 4/2009 | 6/2014 | |||||||
3 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 213 - 312 | 1 | 3 | 1.3.2012 | 1/2017 | 7/2019 | ||||||
4 | 3/2020 | R2 | 9,1 km | 4 | 267 mil. € | 8 780 - 11 203 | 57 - 108 | 3 | 4 | 9/2018 | 3/2020 | |||||||
5 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 10 334 - 11 542 | 230 - 281 | 2 | 2 | 07/2010 | 7/2012 | 3/2021 | ||||||
6 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 10 088 - 50 895 | 90 - 464 | 2 | 1 | 11/2013 | 10/2020 | 10/2021 | |||||
7 | 3. | 3/2022 | D1 | 3,5 km | 8 | 149 mil. € | 62 652 | . . . | 530 | 1 | 1 | 1.10.2016 | 5/2020 | 3/2022 | ||||
8 | 4. | 9/2022 | R4 | 10,2 km | 4 | 299 mil. € | 22 341 - 30 731 | 367 - 547 | 1 | 3 | 1.5.2017 | 8/2021 | 9/2022 | |||||
9 | 5. | 4/2023 | R1 | 8,1 km | 4 | 173 mil. € | 12 387 - 17 316 | 109 - 210 | 2 | 3 | 09/2019 | 3/2023 | 4/2023 | |||||
10 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 169 - 482 | 3 | 3 | 11/2013 | 6/2022 | 7/2023 | |||||
89,2 km |
2 - 8 |
2 407 mil. € |
8 780 - 62 652 | 1,7 |
2,3 |
12/2013 - 7/2023 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku