dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
186,6 km |
2 - 8 |
27 407 m |
4 467 mil. € |
2,6 |
2,9 |
|||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | R 22,5/100 | 1 397 m | Šalková | 173 mil. € | 2 | 3 | |||
2 | 3. | 3/2022 | D1 | 3,5 km | 8 | D 41/120 | 1 352 m | Ivanka sever | 149 mil. € | 1 | 1 | |||
3 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R 22,5/100, plánované v 1/2-profile | 411 m | 105 mil. € | 2 | 2 | ||||
4 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | 1 544 m | Dlhá nad Oravou | 77 mil. € | 2 | 2 | |||
5 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | 2 006 m | Zemné | 227 mil. € | 4 | 4 | |||
6 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 377 m | Holice s I/63, D. Streda s III/06325 | 191 mil. € | 4 | 5 | |||
7 | 6. | 7/2023 | R2 | 6,8 km | 4 | R 24,5/100 | 2 725 m | Ludvíkov Dvor, Haniska | 171 mil. € | 3 | 3 | |||
8 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 1 640 m | Trenčín juh, Trenčianska Turná | 143 mil. € | 3 | 4 | |||
9 | 12. | 7/2024 | R3 | 6,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 892 m | privádzač Krupina | 70 mil. € | 2 | 2 | |||
10 | 19. | 6/2025 | R4 | 8,2 km | 2 | R 24,5/100, plánované v 1/2-profile | 487 m | Svidník sever | 94 mil. € | 3 | 3 | |||
11 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | 420 m | Mliečany s II/507, Dolný Bar | 161 mil. € | 4 | 5 | |||
12 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | 1 929 m | Trenčianske Mitice | 277 mil. € | 2 | 2 | |||
13 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | 2 956 m | Podbiel | 199 mil. € | 2 | 3 | |||
14 | 4. | 9/2022 | R4 | 10,2 km | 4 | R 24,5/100 | 1 638 m | Kapušany | 299 mil. € | 1 | 3 | |||
15 | 10. | 4/2024 | D1 | 3,8 km | 2 | R 11,5/80 | 1 030 m | 57 mil. € | 3 | 5 | ||||
16 | 18. | 4/2025 | D1 | 1,1 km | 2 | D 11,5/80 | 158 m | 12 mil. € | 2 | 1 | ||||
17 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 095 m | Rožňava, Jablonov nad Turňou | 272 mil. € | 3 | 2 | |||
18 | 11. | 6/2024 | R1 | 2,7 km | 4 | R 24,5/80 | 351 m | Ružomberok juh, Ružomberok východ | 155 mil. € | 4 | 3 | |||
19 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 206 m | 59 mil. € | 3 | 4 | ||||
20 | 7. | 2/2024 | D1 | 13,5 km | 4 | D 26,5/100 | 1 330 m | Turany 2, Hubová | 1 235 mil. € | 1 | 1 | |||
21 | 13. | 8/2024 | R2 | 8,3 km | 2 | R 22,5/100, plánované v 1/2-profile | 457 m | Zacharovce, Bátka | 169 mil. € | 2 | 2 | |||
22 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | 2 006 m | Nové Zámky | 172 mil. € | 4 | 4 | |||
186,6 km |
2 - 8 |
27 407 m |
4 467 mil. € |
2,6 |
2,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku