dátum |
plánovaný
|
odhad NDS
|
pozemky
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||||
22 úsekov |
186,6 km |
2 - 8 |
4 467 mil. € |
286,6 mil. € |
94,8 min. |
4 001 - 62 652 | 2,6 |
2,9 |
9/2025 - 12/2030 | |||||||||
1 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 191 mil. € | 31,9 mil. € | 7,0 min. | 6 428 - 9 084 | 4 | 5 | 6,0 | 9/2028 (+3,5) | ||||
2 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | 161 mil. € | 25,1 mil. € | 6 403 - 9 478 | 4 | 5 | 5,0 | 5/2029 (+3,5) | |||||
3 | 10. | 4/2024 | D1 | 3,8 km | 2 | R 11,5/80 | 57 mil. € | 2,5 mil. € | 10 312 | 3 | 5 | 8,0 | 4/2027 (+4,1) | |||||
4 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | 227 mil. € | 7,5 mil. € | 4 | 4 | 5,0 | 4/2029 (+4,1) | ||||||
5 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 143 mil. € | 26,4 mil. € | 4,5 min. | 12 157 | 3 | 4 | 7,0 | 12/2028 (+4,3) | ||||
6 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 8,7 mil. € | 2,3 min. | 12 862 | 3 | 4 | 6,0 | 10/2028 (+4,2) | ||||
7 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | 172 mil. € | 2,8 mil. € | 4 | 4 | 6,0 | 4/2029 (+4,1) | ||||||
8 | 5. | 4/2023 | R1 | 8,1 km | 4 | R 22,5/100 | 173 mil. € | 16,6 mil. € | 12 387 - 17 316 | 2 | 3 | 9,0 | 4/2026 (+3,7) | |||||
9 | 6. | 7/2023 | R2 | 6,8 km | 4 | R 24,5/100 | 171 mil. € | 35,4 mil. € | 11 764 - 50 895 | 3 | 3 | 9,0 | 7/2026 (+4,3) | |||||
10 | 19. | 6/2025 | R4 | 8,2 km | 2 | R 24,5/100, plánované v 1/2-profile | 94 mil. € | 2,1 mil. € | 7,0 min. | 4 001 | 3 | 3 | 7,0 | 6/2027 (+4,7) | ||||
11 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | 199 mil. € | 7,1 mil. € | 11,0 min. | 5 550 - 9 787 | 2 | 3 | 6,0 | 10/2028 (+4,1) | ||||
12 | 4. | 9/2022 | R4 | 10,2 km | 4 | R 24,5/100 | 299 mil. € | 22,4 mil. € | 22 341 - 30 731 | 1 | 3 | 10,0 | 1/2027 (+4,8) | |||||
13 | 11. | 6/2024 | R1 | 2,7 km | 4 | R 24,5/80 | 155 mil. € | 8,3 mil. € | 16 268 | 4 | 3 | 6,0 | 6/2026 (+3,5) | |||||
14 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R 22,5/100, plánované v 1/2-profile | 105 mil. € | 2,3 mil. € | 5,5 min. | 5 304 | 2 | 2 | 8,0 | 3/2026 (+4,7) | ||||
15 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | 77 mil. € | 5,1 mil. € | 5,5 min. | 2 | 2 | 6,0 | 10/2028 (+4,1) | |||||
16 | 12. | 7/2024 | R3 | 6,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 70 mil. € | 5,8 mil. € | 6 706 - 9 733 | 2 | 2 | 6,0 | 7/2026 (+2,7) | |||||
17 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | 277 mil. € | 29,5 mil. € | 13,0 min. | 9 654 - 12 079 | 2 | 2 | 6,0 | 10/2028 (+3,2) | ||||
18 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 272 mil. € | 10,4 mil. € | 14,5 min. | 5 792 - 7 064 | 3 | 2 | 8,0 | 12/2029 (+5,4) | ||||
19 | 13. | 8/2024 | R2 | 8,3 km | 2 | R 22,5/100, plánované v 1/2-profile | 169 mil. € | 5,8 mil. € | 7,5 min. | 5 277 - 6 250 | 2 | 2 | 8,0 | 8/2026 (+5,1) | ||||
20 | 3. | 3/2022 | D1 | 3,5 km | 8 | D 41/120 | 149 mil. € | 11,1 mil. € | 62 652 | . . . | 1 | 1 | 8,0 | 9/2025 (+4,6) | ||||
21 | 18. | 4/2025 | D1 | 1,1 km | 2 | D 11,5/80 | 12 mil. € | 0,8 mil. € | 2 | 1 | 7,0 | 1/2027 (+5,0) | ||||||
22 | 7. | 2/2024 | D1 | 13,5 km | 4 | D 26,5/100 | 1 235 mil. € | 19,1 mil. € | 17,0 min. | 13 676 - 21 949 | 1 | 1 | 7,0 | 12/2030 (+4,5) | ||||
22 úsekov |
186,6 km |
2 - 8 |
4 467 mil. € |
286,6 mil. € |
94,8 min. |
4 001 - 62 652 | 2,6 |
2,9 |
9/2025 - 12/2030 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku