dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
27 úsekov |
264,9 km |
2 - 8 |
6 381 mil. € |
2,6 |
3,1 |
1/2027 - 6/2033 |
|||||||||
1 | 4. | 9/2022 | R4 | 10,2 km | 4 | Okruhliak 1917 m | 299 mil. € | 12 070 | 1 | 3 | 1/2027 (+4,8) | ||||
2 | 7. | 2/2024 | D1 | 13,5 km | 4 | Korbeľka 5868 m | 1 235 mil. € | 25 191 | 1 | 1 | 12/2030 (+4,5) | ||||
3 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 191 mil. € | 25 850 | 4 | 5 | 9/2028 (+3,5) | |||||
4 | 10. | 4/2024 | D1 | 3,8 km | 2 | 57 mil. € | 4 963 | 3 | 5 | 4/2027 (+4,1) | |||||
5 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 227 mil. € | 12 104 | 4 | 4 | 4/2029 (+4,1) | |||||
6 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | 172 mil. € | 10 118 | 4 | 4 | 4/2029 (+4,1) | |||||
7 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | 161 mil. € | 16 380 | 4 | 5 | 5/2029 (+3,5) | |||||
8 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | Soroška 4282 m | 272 mil. € | 6 302 | 3 | 2 | 12/2029 (+5,4) | ||||
9 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 4 984 | 2 | 1 | 1/2027 (+5,0) | |||||
10 | 19. | 6/2025 | R4 | 8,2 km | 2 | 94 mil. € | 6 944 | 3 | 3 | 6/2027 (+4,7) | |||||
11 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 5 660 | 2 | 2 | 10/2028 (+4,1) | |||||
12 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | Biela Skala 630 m | 199 mil. € | 6 090 | 2 | 3 | 10/2028 (+4,1) | ||||
13 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | Mníchova Lehota 180 m | 277 mil. € | 12 676 - 16 847 | 2 | 2 | 10/2028 (+3,2) | ||||
14 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 13 396 | 3 | 4 | 10/2028 (+4,2) | |||||
15 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | 12 125 | 3 | 4 | 12/2028 (+4,3) | |||||
16 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 28 654 | 2 | 4 | 1/2029 (+3,0) | |||||
17 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | po Lučenec 9 371, ďalej 8 954 | 4 | 4 | 4/2028 (+4,8) | |||||
18 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 38 080 | 1 | 1 | 5/2029 (+5,1) | |||||
19 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 105 mil. € | 11 489 | 2 | 2 | 8/2029 (+3,8) | |||||
20 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 125 mil. € | po R. Sobotu 7 978, ďalej 8 783 | 4 | 4 | 8/2028 (+5,1) | |||||
21 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 14 868 | 4 | 3 | 10/2028 (+3,5) | |||||
22 | 31. | 11/2026 | D3 | 4,0 km | 4 | Horelica 590 m | 179 mil. € | 26 769 | 1 | 2 | 11/2030 (+6,4) | ||||
23 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | Karpaty 10 990 m | 772 mil. € | 20 978 | 3 | 4 | 6/2033 (+3,3) | ||||
24 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 224 mil. € | 15 407 | 3 | 5 | 12/2029 (+2,8) | |||||
25 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 234 mil. € | 83 524 | 2 | 1 | 6/2030 (+6,9) | |||||
26 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 116 mil. € | 7 822 | 2 | 3 | 6/2030 (+3,7) | |||||
27 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 122 mil. € | 4 129 | 2 | 2 | 6/2030 (+3,7) | |||||
27 úsekov |
264,9 km |
2 - 8 |
6 381 mil. € |
2,6 |
3,1 |
1/2027 - 6/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku