dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
295,4 km |
2 - 8 |
7 166 mil. € |
3,1 |
3,2 |
1/2029 - 9/2033 |
||||||||||
1 | 46. | 3/2029 | ![]() | D1 | 7,3 km | 4 | 26,5/100 | 321 mil. € | 51 | 3 | 3 | 9/2033 (+5,8) | |||
2 | 39. - 40. | 3/2028 | ![]() | D1 | 19,9 km | 6 | D 33,5/120 | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 266 - 354 | 3 | 2 | 9/2032 (+5,6) | ||
3 | 34. - 36. | 6/2027 | ![]() | D1 | 10,6 km | 8 | D 41/120 | Senec | 234 mil. € | 530 | 2 | 1 | 6/2030 (+6,9) | ||
4 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | 2/2033 (+4,5) | ||||
5 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||
6 | 39. - 40. | 3/2028 | ![]() | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | Nováky - západ | 112 mil. € | 120 - 202 | 2 | 4 | 3/2031 (+5,9) | ||
7 | 14. - 15. | 10/2024 | ![]() | R7 | 23,5 km | 2 | R 11,5/120 | Zemné | 227 mil. € | 4 | 4 | 4/2029 (+4,1) | |||
8 | 34. - 36. | 6/2027 | ![]() | R4 | 6,5 km | 2 | R 24,5/100, plánované v 1/2-profile | Kuková | 116 mil. € | 69 - 141 | 2 | 3 | 6/2030 (+3,7) | ||
9 | 48. - 49. | 9/2029 | ![]() | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 69 - 107 | 5 | 5 | 9/2032 (+5,6) | |||
10 | 37. - 38. | 2/2028 | ![]() | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | Jablonov n.Turňou | 73 mil. € | 54 | 5 | 4 | 2/2031 (+4,1) | ||
11 | 25. | 1/2026 | ![]() | D3 | 10,8 km | 4 | D 24,5/80 (100) | Krásno nad Kysucou | 309 mil. € | 62 - 103 | 2 | 4 | 1/2029 (+3,0) | ||
12 | 28. - 29. | 8/2026 | ![]() | R4 | 4,0 km | 4 | R 24,5/100 | Lipníky | 105 mil. € | 181 | 2 | 2 | 8/2029 (+3,8) | ||
13 | 16. - 17. | 12/2024 | ![]() | R7 | 8,4 km | 4 | R 24,5/120 | Mliečany s II/507, Dolný Bar | 161 mil. € | 32 - 113 | 4 | 5 | 5/2029 (+3,5) | ||
14 | 32. - 33. | 12/2026 | ![]() | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Moldava nad Bodvou, Šaca | 224 mil. € | 100 - 105 | 3 | 5 | 12/2029 (+2,8) | ||
15 | 48. - 49. | 9/2029 | ![]() | R3 | 7,9 km | 2 | R 24,5/120(100), plánované v 1/2-profile | Mošovce,
Horná Štubňa | 71 mil. € | 30 - 78 | 4 | 3 | 9/2032 (+4,1) | ||
16 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | D 24,5/80 | 179 mil. € | 564 | 1 | 2 | 11/2030 (+6,4) | |||
17 | 41. | 9/2028 | ![]() | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 82 | 2 | 4 | 9/2031 (+5,4) | |||
18 | 34. - 36. | 6/2027 | ![]() | R4 | 7,0 km | 2 | R 24,5/100, plánované v 1/2-profile | Okrúhle | 122 mil. € | 42 - 71 | 2 | 2 | 6/2030 (+3,7) | ||
19 | 16. - 17. | 12/2024 | ![]() | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | Rožňava, Jablonov nad Turňou | 272 mil. € | 20 - 78 | 3 | 2 | 12/2029 (+5,4) | ||
20 | 37. - 38. | 2/2028 | ![]() | R1 | 14,9 km | 4 | R 24,5/80 | Slovenská Ľupča, Korytnica | 785 mil. € | 76 - 172 | 3 | 3 | 2/2031 (+6,9) | ||
21 | 44. - 45. | 2/2029 | ![]() | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Plešivec | 176 mil. € | 49 - 72 | 5 | 5 | 2/2032 (+4,9) | ||
22 | 7. | 2/2024 | ![]() | D1 | 13,5 km | 4 | D 26,5/100 | Turany 2, Hubová | 1 235 mil. € | 81 - 144 | 1 | 1 | 12/2030 (+4,5) | ||
23 | 47. | 7/2029 | ![]() | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Turňa nad Bodvou | 117 mil. € | 56 - 84 | 5 | 4 | 7/2032 (+5,3) | ||
24 | 14. - 15. | 10/2024 | ![]() | R7 | 14,3 km | 2 | R 11,5/120 | Nové Zámky | 172 mil. € | 4 | 4 | 4/2029 (+4,1) | |||
25 | 42. - 43. | 11/2028 | ![]() | R3 | 5,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Šahy | 63 mil. € | 112 - 134 | 3 | 2 | 11/2030 (+5,2) | ||
26 | 42. - 43. | 11/2028 | ![]() | R4 | 7,9 km | 2 | R 24,5/100, plánované v 1/2-profile | Hunkovce, Vyšný Komárnik | 129 mil. € | 21 - 33 | 4 | 3 | 11/2031 (+4,8) | ||
27 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | D 24,5/80 | Brodno, Kysucké Nové Mesto | 410 mil. € | 118 - 245 | 1 | 1 | 5/2029 (+5,1) | ||
295,4 km |
2 - 8 |
7 166 mil. € |
3,1 |
3,2 |
1/2029 - 9/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku