dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
24 úsekov |
2 - 8 |
6 048 mil. € |
128,2 km |
3,3 |
3,1 |
||||||||
1 | 7. | 2/2024 | ![]() | D1 | 4 | 1 235 mil. € | 13,5 km | 1 888 - 3 445 | 1 | 1 | |||
2 | 31. | 11/2026 | ![]() | D3 | 4 | 179 mil. € | 4,0 km | 3 812 | 1 | 2 | |||
3 | 32. - 33. | 12/2026 | ![]() | D4 | 4 | 772 mil. € | 3 | 4 | |||||
4 | 34. - 36. | 6/2027 | ![]() | D1 | 8 | 234 mil. € | 6 104 | 2 | 1 | ||||
5 | 34. - 36. | 6/2027 | ![]() | R4 | 2 | 116 mil. € | 6,4 km | 750 - 771 | 2 | 3 | |||
6 | 34. - 36. | 6/2027 | ![]() | R4 | 2 | 122 mil. € | 7,0 km | 1 298 - 1 289 | 2 | 2 | |||
7 | 37. - 38. | 2/2028 | ![]() | R1 | 4 | 785 mil. € | 830 - 1 460 | 3 | 3 | ||||
8 | 37. - 38. | 2/2028 | ![]() | R2 | 2 | 73 mil. € | 7,8 km | 711 | 5 | 4 | |||
9 | 39. - 40. | 3/2028 | ![]() | D1 | 6 | 321 mil. € | 3 862 - 4 344 | 3 | 2 | ||||
10 | 39. - 40. | 3/2028 | ![]() | R2 | 2 | 112 mil. € | 1 189 - 1 517 | 2 | 4 | ||||
11 | 41. | 9/2028 | ![]() | R2 | 2 | 235 mil. € | 11,5 km | 1 259 | 2 | 4 | |||
12 | 42. - 43. | 11/2028 | ![]() | R4 | 2 | 129 mil. € | 8,3 km | 826 - 1 507 | 4 | 3 | |||
13 | 42. - 43. | 11/2028 | ![]() | R3 | 2 | 63 mil. € | 1 111 - 1 112 | 3 | 2 | ||||
14 | 44. - 45. | 2/2029 | ![]() | R2 | 2 | 176 mil. € | 17,0 km | 787 - 807 | 5 | 5 | |||
15 | 44. - 45. | 2/2029 | ![]() | D4 | 4 | 133 mil. € | 5 | 5 | |||||
16 | 46. | 3/2029 | ![]() | D1 | 4 | 321 mil. € | 7,3 km | 1 767 | 3 | 3 | |||
17 | 47. | 7/2029 | ![]() | R2 | 2 | 117 mil. € | 14,0 km | 881 - 1 194 | 5 | 4 | |||
18 | 48. - 49. | 9/2029 | ![]() | R2 | 2 | 93 mil. € | 9,8 km | 780 - 984 | 5 | 5 | |||
19 | 48. - 49. | 9/2029 | ![]() | R3 | 2 | 71 mil. € | 1 024 - 1 288 | 4 | 3 | ||||
20 | 50. - 52. | 5/2030 | ![]() | R4 | 2 | 133 mil. € | 8,5 km | 349 - 902 | 4 | 3 | |||
21 | 50. - 52. | 5/2030 | ![]() | R4 | 2 | 124 mil. € | 7,0 km | 1 289 - 1 580 | 3 | 3 | |||
22 | 50. - 52. | 5/2030 | ![]() | R4 | 2 | 101 mil. € | 6,0 km | 1 492 - 1 737 | 4 | 3 | |||
23 | 53. - 54. | 7/2030 | ![]() | R6 | 2 | 182 mil. € | 632 | 4 | 3 | ||||
24 | 53. - 54. | 7/2030 | ![]() | R6 | 2 | 222 mil. € | 427 - 551 | 4 | 3 | ||||
24 úsekov |
2 - 8 |
6 048 mil. € |
128,2 km |
3,3 |
3,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku