dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
315,5 km |
2 - 6 |
6 564 mil. € |
3,6 |
3,4 |
12/2026 - 8/2031 |
||||||||||
1 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | Od roku 2017 prebieha proces posúdenia vplyvov na životné prostredie (EIA). | 12/2026 | |||||
2 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 785 mil. € | 3 | 3 | 3/2024 | žiadna | 2/2028 | ||||
3 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 | 4 | 2/2025 | žiadna | 2/2028 | ||||
4 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 3 | 2 | 7/2025 | 6/2024 | žiadna | 3/2028 | |||
5 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 112 mil. € | 2 | 4 | 9/2025 | žiadna | 3/2028 | ||||
6 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 2 | 4 | 4/2026 | žiadna | 9/2028 | ||||
7 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 129 mil. € | 4 | 3 | 11/2025 | žiadna | 11/2028 | ||||
8 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 | 5 | 1/2026 | žiadna | 2/2029 | ||||
9 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | žiadna | 2/2029 | |||||
10 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 3 | 3 | 6/2024 | žiadna | 3/2029 | ||||
11 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 | 4 | 7/2026 | žiadna | 7/2029 | ||||
12 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 5 | 5 | 9/2026 | žiadna | 9/2029 | ||||
13 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 2/2027 | žiadna | 9/2029 | ||||
14 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 4 | 3 | 5/2027 | žiadna | 5/2030 | ||||
15 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 | 3 | 5/2027 | žiadna | 5/2030 | ||||
16 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 4 | 3 | 8/2027 | žiadna | 5/2030 | ||||
17 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 4 | 3 | 2/2028 | žiadna | 7/2030 | ||||
18 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 4 | 3 | 2/2028 | žiadna | 7/2030 | ||||
19 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 4 | 4 | 3/2029 | žiadna | 5/2031 | ||||
20 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 4 | 4 | 3/2029 | žiadna | 5/2031 | ||||
21 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 3 | 5 | 6/2027 | žiadna | 6/2031 | ||||
22 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 3 | 3 | 9/2029 | žiadna | 6/2031 | ||||
23 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 2 | 2 | 9/2028 | žiadna | 7/2031 | ||||
24 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 94 mil. € | 4 | 2 | 1/2029 | žiadna | 8/2031 | ||||
25 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 3 | 2 | 1/2029 | žiadna | 8/2031 | ||||
315,5 km |
2 - 6 |
6 564 mil. € |
3,6 |
3,4 |
12/2026 - 8/2031 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku