dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||
279,2 km |
2 - 6 |
5 428 mil. € |
3,9 |
3,5 |
2/2032 - 6/2036 |
|||||||||
1 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | 8/2007 | 6/2033 (+3,3) | |||
2 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D 33,5/120 | 321 mil. € | 3 | 2 | 11/2008 | 9/2032 (+5,6) | |||
3 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 176 mil. € | 5 | 5 | 7/2010 | 2/2032 (+4,9) | |||
4 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | 1/2007 | 2/2033 (+4,5) | |||
5 | 46. | 3/2029 | D1 | 7,3 km | 4 | 26,5/100 | 321 mil. € | 3 | 3 | 2/2009 | 9/2033 (+5,8) | |||
6 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 117 mil. € | 5 | 4 | 5/2008 | 7/2032 (+5,3) | |||
7 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 5 | 5 | 12/2007 | 9/2032 (+5,6) | |||
8 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 71 mil. € | 4 | 3 | 5/2008 | 9/2032 (+4,1) | |||
9 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 133 mil. € | 4 | 3 | 7/2004 | 5/2033 (+6,1) | |||
10 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 124 mil. € | 3 | 3 | 7/2004 | 5/2033 (+6,1) | |||
11 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 101 mil. € | 4 | 3 | 7/2004 | 5/2033 (+6,1) | |||
12 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R 11,5/100 (80) | 182 mil. € | 4 | 3 | 4/2005 | 7/2033 (+4,3) | |||
13 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R 11,5/100 (80) | 222 mil. € | 4 | 3 | 4/2005 | 7/2033 (+4,3) | |||
14 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | R 24,5/80 | 406 mil. € | 4 | 4 | 9/2009 | 5/2033 (+10,2) | |||
15 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | R 24,5/80 | 339 mil. € | 4 | 4 | 9/2009 | 5/2033 (+10,2) | |||
16 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 3 | 5 | 1/2009 | 6/2036 (+2,3) | |||
17 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | R 24,5/120 (100) | 191 mil. € | 3 | 3 | 5/2008 | 6/2034 (+7,0) | |||
18 | 59. | 7/2031 | R2 | 17,5 km | 4 | R 24,5/100 | 287 mil. € | 2 | 2 | 5/2006 | 7/2034 (+10,0) | |||
19 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | R 11,5/80 (60) | 94 mil. € | 4 | 2 | 5/2007 | 8/2034 (+2,1) | |||
20 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | R 11,5/80 (60) | 129 mil. € | 3 | 2 | 5/2007 | 8/2034 (+2,1) | |||
21 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | D 33,5/120 | 90 mil. € | 5 | 5 | 11/2009 | 10/2035 (+5,6) | |||
22 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | D 33,5/120 | 107 mil. € | 5 | 5 | 11/2009 | 10/2035 (+5,9) | |||
279,2 km |
2 - 6 |
5 428 mil. € |
3,9 |
3,5 |
2/2032 - 6/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku