661,2 km |
2 - 8 |
13 433 mil. € |
1 059,1 mil. € |
2 561 - 93 344 | 2,8 |
3,0 |
12/2019 - 10/2021 | |||||||||
1 | 6/2017 | D1 | 7,9 km | 4 | D 26,5/100 | Prešov západ, Prešov juh | 434 mil. € | 43,9 mil. € | 19 072 - 21 988 | 1 | 2 | 10/2021 | ||||
2 | 7/2016 | R7 | 6,4 km | 4 - 6 | R 31,5/120 | Prievoz | 70,3 mil. € | 27 633 - 44 493 | . . . | 1 | 1 | 10/2021 | ||||
3 | 1/2014 | D1 | 11,3 km | 4 | D 26,5/100 | 517 mil. € | 14,7 mil. € | 23 579 - 28 413 | 2 | 3 | 1/2021 (0,0) | |||||
4 | 12/2017 | D1 | 2,6 km | 4 | R 22,5/80 | 39 mil. € | 10,3 mil. € | 14 624 | 1 | 1 | 1/2021 (0,0) | |||||
5 | 12/2016 | D3 | 5,7 km | 4 | D 24,5/80 | Čadca Podzávoz, Čadca Bukov | 269 mil. € | 16,6 mil. € | 11 465 - 18 743 | 1 | 2 | 12/2020 (0,0) | ||||
6 | 7/2016 | R7 | 17,4 km | 4 | R 24,5/120 | Šamorín, Holice | 30,8 mil. € | 8 544 - 13 236 | 2 | 3 | 7/2020 (0,0) | |||||
7 | 7/2016 | R7 | 8,4 km | 4 | R 31,5/120 | Dunajská Lužná | 25,1 mil. € | 13 102 - 19 993 | 1 | 1 | 7/2020 (0,0) | |||||
8 | 11/2016 | D1 | 14,4 km | 4 | D 26,5/120 | Budimír (Košice-Sever), Košické Olšany, Bidovce | 241 mil. € | 31,8 mil. € | 3 166 - 11 562 | 2 | 2 | 12/2019 (0,0) | ||||
9 | 46. | 3/2029 | D1 | 7,3 km | 4 | 26,5/100 | 321 mil. € | 0,5 mil. € | 10 359 | 3 | 3 | |||||
10 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D 33,5/120 | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 37,5 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | |||
11 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | D 41/120 | Senec | 234 mil. € | 34,4 mil. € | 62 652 | . . . | 2 | 1 | |||
12 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5,5 mil. € | 5 | 5 | ||||||
13 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 2,9 mil. € | 3 | 4 | ||||||
14 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | Dlhá nad Oravou | 77 mil. € | 5,1 mil. € | 2 | 2 | |||||
15 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | Zemné | 227 mil. € | 7,5 mil. € | 4 | 4 | |||||
16 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | R 11,5/80 (60) | Valaská Dubová, Likavka | 94 mil. € | 12,0 mil. € | 7 211 | 4 | 2 | ||||
17 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | R 24,5/100, plánované v 1/2-profile | Kuková | 116 mil. € | 12,6 mil. € | 6 651 - 9 113 | 2 | 3 | ||||
18 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 6,5 mil. € | 6 452 - 10 032 | 5 | 5 | |||||
19 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | Holice s I/63, D. Streda s III/06325 | 191 mil. € | 31,9 mil. € | 6 428 - 9 084 | 4 | 5 | ||||
20 | 12/2013 | D1 | 14,9 km | 4 | D 26,5/100 | Hubová, Likavka, Ivachnová | 341 mil. € | 22,9 mil. € | 12 491 - 24 900 | 1 | 1 | |||||
21 | 7/2016 | D4 | 4,4 km | 4 - 6 | D 33,5/120, D 26,5/120 | Čierna voda, Rača | 50,2 mil. € | 1 | 2 | |||||||
22 | 7/2016 | D4 | 22,6 km | 4 - 6 | D 33,5/120, D 26,5/120 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 179,5 mil. € | 32 336 - 93 344 | . . . | 1 | 2 | |||||
23 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | R 24,5/80 | Liptovská Osada | 406 mil. € | 4,6 mil. € | 7 784 | 4 | 4 | ||||
24 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | Trenčín juh, Trenčianska Turná | 143 mil. € | 26,4 mil. € | 12 157 | 3 | 4 | ||||
25 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | Kuková | 133 mil. € | 6,0 mil. € | 5 814 - 7 518 | 4 | 3 | ||||
26 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | Krásno nad Kysucou | 309 mil. € | 15,4 mil. € | 14 176 - 14 186 | 2 | 4 | ||||
27 | 19. | 6/2025 | R4 | 8,2 km | 2 | R 24,5/100, plánované v 1/2-profile | Svidník sever | 94 mil. € | 2,1 mil. € | 4 001 | 3 | 3 | ||||
28 | 6/2014 | D1 | 13,5 km | 4 | D 26,5/100 | Lietavská Lúčka | 555 mil. € | 2,4 mil. € | 22 691 - 32 334 | 1 | 2 | |||||
29 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | R 24,5/100 | Lipníky | 105 mil. € | 8,5 mil. € | 14 625 | 2 | 2 | ||||
30 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | R 24,5/80 | 339 mil. € | 4,8 mil. € | 9 704 - 13 715 | 4 | 4 | |||||
31 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 9,3 mil. € | 6 969 - 10 726 | 4 | 4 | |||||
32 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | D 33,5/120 | Stupava | 90 mil. € | 4,4 mil. € | 32 968 | . . . | 5 | 5 | |||
33 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | R 24,5/120 (100) | Martin, Rakovo | 191 mil. € | 19,0 mil. € | 14 233 - 18 874 | 3 | 3 | ||||
34 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R 11,5/100 (80) | Púchov západ,
Púchov východ,
Dolné Kočkovce | 182 mil. € | 10,0 mil. € | 7 234 | 4 | 3 | ||||
35 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | Mliečany s II/507, Dolný Bar | 161 mil. € | 25,1 mil. € | 6 403 - 9 478 | 4 | 5 | ||||
36 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | Trenčianske Mitice | 277 mil. € | 29,5 mil. € | 9 654 - 12 079 | 2 | 2 | ||||
37 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Moldava nad Bodvou, Šaca | 224 mil. € | 22,6 mil. € | 10 140 - 11 010 | 3 | 5 | ||||
38 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | R 24,5/120(100), plánované v 1/2-profile | Mošovce,
Horná Štubňa | 71 mil. € | 8,9 mil. € | 5 441 - 8 427 | 4 | 3 | ||||
39 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 28,6 mil. € | 4 151 - 11 477 | 3 | 5 | |||||
40 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | Podbiel | 199 mil. € | 7,1 mil. € | 5 550 - 9 787 | 2 | 3 | ||||
41 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | R 11,5/80 (60) | Široká, Jasenová, v mestskom variante tiež Kocmáľ (Mokraď) a Dolný Kubín stred | 129 mil. € | 6,0 mil. € | 5 586 - 10 745 | 3 | 2 | ||||
42 | 31. | 11/2026 | D3 | 4,0 km | 4 | D 24,5/80 | 179 mil. € | 3,3 mil. € | 15 053 | 1 | 2 | |||||
43 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | Rimavská Sobota | 125 mil. € | 5,5 mil. € | 6 412 - 8 112 | 4 | 4 | ||||
44 | 4. | 9/2022 | R4 | 10,2 km | 4 | R 24,5/100 | Kapušany | 299 mil. € | 22,4 mil. € | 22 341 - 30 731 | 1 | 3 | ||||
45 | 10. | 4/2024 | D1 | 3,8 km | 2 | R 11,5/80 | 57 mil. € | 2,5 mil. € | 10 312 | 3 | 5 | |||||
46 | 18. | 4/2025 | D1 | 1,1 km | 2 | D 11,5/80 | 12 mil. € | 0,8 mil. € | 2 | 1 | ||||||
47 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | Giraltovce | 124 mil. € | 4,8 mil. € | 3 769 - 3 897 | 3 | 3 | ||||
48 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | R 24,5/100, plánované v 1/2-profile | Okrúhle | 122 mil. € | 10,4 mil. € | 3 407 - 3 769 | 2 | 2 | ||||
49 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | Rožňava, Jablonov nad Turňou | 272 mil. € | 10,4 mil. € | 5 792 - 7 064 | 3 | 2 | ||||
50 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | križovatka D1 | 100 mil. € | 2,8 mil. € | 11 611 | 4 | 3 | ||||
51 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | D 33,5/120 | Stupava | 107 mil. € | 3,9 mil. € | 5 | 5 | |||||
52 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R 24,5/100, plánované v 1/2-profile | Stročín | 101 mil. € | 6,1 mil. € | 3 782 - 6 302 | 4 | 3 | ||||
53 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Plešivec | 176 mil. € | 10,4 mil. € | 5 189 - 6 389 | 5 | 5 | ||||
54 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 8,7 mil. € | 12 862 | 3 | 4 | |||||
55 | 7. | 2/2024 | D1 | 13,5 km | 4 | D 26,5/100 | Turany 2, Hubová | 1 235 mil. € | 19,1 mil. € | 13 676 - 21 949 | 1 | 1 | ||||
56 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Turňa nad Bodvou | 117 mil. € | 7,5 mil. € | 5 809 - 8 826 | 5 | 4 | ||||
57 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | Nové Zámky | 172 mil. € | 2,8 mil. € | 4 | 4 | |||||
58 | 59. | 7/2031 | R2 | 17,5 km | 4 | R 24,5/100 | Rákoš, Zvolenská Slatina | 287 mil. € | 14,9 mil. € | 12 819 - 29 988 | 2 | 2 | ||||
59 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R 11,5/100 (80) | Mestečko | 222 mil. € | 11,0 mil. € | 2 561 - 5 054 | 4 | 3 | ||||
60 | 27. | 5/2026 | D3 | 11,2 km | 4 | D 24,5/80 | Brodno, Kysucké Nové Mesto | 410 mil. € | 18,4 mil. € | 13 886 - 21 743 | 1 | 1 | ||||
661,2 km |
2 - 8 |
13 433 mil. € |
1 059,1 mil. € |
2 561 - 93 344 | 2,8 |
3,0 |
12/2019 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku