plánovaný
|
odhad NDS
|
stavebné práce
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
skutočnosť podľa zmluvy
|
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
40 úsekov |
486,9 km |
2 - 6 |
9 984 mil. € |
229,3 min. |
1 698 - 50 895 | 2,9 |
3,2 |
3/2026 - 8/2037 | |||||||
1 | R4 | 10,2 km | 4 | 299 mil. € | 22 341 - 30 731 | 1 | 3 | 1/2027 (+4,8) | |||||||
2 | R1 | 8,1 km | 4 | 173 mil. € | 12 387 - 17 316 | 2 | 3 | 4/2026 (+3,7) | |||||||
3 | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 7/2026 (+4,3) | |||||||
4 | D1 | 13,5 km | 4 | 1 235 mil. € | 17,0 min. | 13 676 - 21 949 | 1 | 1 | 12/2030 (+4,5) | ||||||
5 | R2 | 6,2 km | 2 | 105 mil. € | 5,5 min. | 5 304 | 2 | 2 | 3/2026 (+4,7) | ||||||
6 | R7 | 9,4 km | 4 | 191 mil. € | 7,0 min. | 6 428 - 9 084 | 4 | 5 | 9/2028 (+3,5) | ||||||
7 | D1 | 3,8 km | 2 | 57 mil. € | 10 312 | 3 | 5 | 4/2027 (+4,1) | |||||||
8 | R1 | 2,7 km | 4 | 155 mil. € | 16 268 | 4 | 3 | 6/2026 (+3,5) | |||||||
9 | R3 | 6,5 km | 2 | 70 mil. € | 6 706 - 9 733 | 2 | 2 | 7/2026 (+2,7) | |||||||
10 | R2 | 8,3 km | 2 | 169 mil. € | 7,5 min. | 5 277 - 6 250 | 2 | 2 | 8/2026 (+5,1) | ||||||
11 | R7 | 23,5 km | 2 | 227 mil. € | 4 | 4 | 4/2029 (+4,1) | ||||||||
12 | R7 | 14,3 km | 2 | 172 mil. € | 4 | 4 | 4/2029 (+4,1) | ||||||||
13 | R7 | 8,4 km | 4 | 161 mil. € | 6 403 - 9 478 | 4 | 5 | 5/2029 (+3,5) | |||||||
14 | R2 | 14,1 km | 2 | 272 mil. € | 14,5 min. | 5 792 - 7 064 | 3 | 2 | 12/2029 (+5,4) | ||||||
15 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 1/2027 (+5,0) | ||||||||
16 | R4 | 8,2 km | 2 | 94 mil. € | 7,0 min. | 4 001 | 3 | 3 | 6/2027 (+4,7) | ||||||
17 | R3 | 4,9 km | 2 | 77 mil. € | 5,5 min. | 2 | 2 | 10/2028 (+4,1) | |||||||
18 | R3 | 8,3 km | 2 | 199 mil. € | 11,0 min. | 5 550 - 9 787 | 2 | 3 | 10/2028 (+4,1) | ||||||
19 | R2 | 16,0 km | 4 | 277 mil. € | 13,0 min. | 9 654 - 12 079 | 2 | 2 | 10/2028 (+3,2) | ||||||
20 | R2 | 2,7 km | 4 | 59 mil. € | 2,3 min. | 12 862 | 3 | 4 | 10/2028 (+4,2) | ||||||
21 | R2 | 6,1 km | 4 | 143 mil. € | 4,5 min. | 12 157 | 3 | 4 | 12/2028 (+4,3) | ||||||
22 | D3 | 10,8 km | 4 | 309 mil. € | 8,5 min. | 14 176 - 14 186 | 2 | 4 | 1/2029 (+3,0) | ||||||
23 | R2 | 20,7 km | 2 | 211 mil. € | 15,0 min. | 6 969 - 10 726 | 4 | 4 | 4/2028 (+4,8) | ||||||
24 | D3 | 11,2 km | 4 | 410 mil. € | 13,0 min. | 13 886 - 21 743 | 1 | 1 | 5/2029 (+5,1) | ||||||
25 | R4 | 4,0 km | 4 | 105 mil. € | 4,0 min. | 14 625 | 2 | 2 | 8/2029 (+3,8) | ||||||
26 | R2 | 10,6 km | 2 | 125 mil. € | 9,0 min. | 6 412 - 8 112 | 4 | 4 | 8/2028 (+5,1) | ||||||
27 | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 4 | 3 | 10/2028 (+3,5) | |||||||
28 | D3 | 4,0 km | 4 | 179 mil. € | 4,0 min. | 15 053 | 1 | 2 | 11/2030 (+6,4) | ||||||
29 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||||||
30 | R2 | 18,0 km | 2 | 224 mil. € | 13,0 min. | 10 140 - 11 010 | 3 | 5 | 12/2029 (+2,8) | ||||||
31 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 6/2036 (+2,3) | |||||||
32 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 10/2035 (+5,6) | ||||||
33 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 10/2035 (+5,9) | ||||||||
34 | D1 | 12,6 km | 4 | 418 mil. € | 12,0 min. | 9 503 - 9 802 | 3 | 3 | 8/2036 (+7,9) | ||||||
35 | D1 | 18,2 km | 4 | 192 mil. € | 17,0 min. | 6 207 - 8 525 | 2 | 2 | 8/2036 (+7,9) | ||||||
36 | D1 | 15,8 km | 4 | 139 mil. € | 16,0 min. | 4 033 - 8 369 | 4 | 3 | 8/2036 (+7,7) | ||||||
37 | D1 | 12,1 km | 4 | 162 mil. € | 8,0 min. | 10 444 - 14 783 | 3 | 3 | 8/2036 (+7,7) | ||||||
38 | D1 | 15,5 km | 4 | 136 mil. € | 15,0 min. | 1 698 - 6 812 | 4 | 3 | 8/2036 (+7,7) | ||||||
39 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | ||||||||
40 | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | |||||||
40 úsekov |
486,9 km |
2 - 6 |
9 984 mil. € |
229,3 min. |
1 698 - 50 895 | 2,9 |
3,2 |
3/2026 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku