plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||
17 úsekov |
454,7 km |
2 - 6 |
5 775 mil. € |
4,1 |
3,9 |
10/2035 - po 2040 |
7. - 32. | ||||
1 | D1 | 12,6 km | 4 | 418 mil. € | 3 | 3 | 8/2036 (+7,9) | 11. | |||
2 | D1 | 18,2 km | 4 | 192 mil. € | 2 | 2 | 8/2036 (+7,9) | 8. | |||
3 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | 7. | |||
4 | D2 | 8,5 km | 6 | 90 mil. € | 5 | 5 | 10/2035 (+5,6) | ||||
5 | D1 | 15,8 km | 4 | 139 mil. € | 4 | 3 | 8/2036 (+7,7) | 9. | |||
6 | R1 | 42,1 km | 4 | 631 mil. € | 5 | 5 | po 2040 | ||||
7 | R8 | 54,9 km | 4 | 1 020 mil. € | 3 | 5 | 6/2036 (+2,3) | 26. | |||
8 | R2 | 49,0 km | 2 | 662 mil. € | 4 | 4 | 8/2037 (+5,9) | ||||
9 | R7 | 29,2 km | 2 | 230 mil. € | 5 | 5 | po 2040 (0,0) | 24. | |||
10 | D1 | 12,1 km | 4 | 162 mil. € | 3 | 3 | 8/2036 (+7,7) | 9. | |||
11 | R3 | 10,3 km | 2 | 92 mil. € | 4 | 2 | po 2040 (0,0) | 7. | |||
12 | D3 | 3,1 km | 4 | 60 mil. € | 5 | 5 | po 2040 (0,0) | ||||
13 | D1 | 15,5 km | 4 | 136 mil. € | 4 | 3 | 8/2036 (+7,7) | 29. | |||
14 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 10/2035 (+5,9) | ||||
15 | R7 | 32,8 km | 2 | 367 mil. € | 5 | 5 | po 2040 (0,0) | 20. | |||
16 | R3 | 58,5 km | 2 | 611 mil. € | 4 | 4 | po 2040 (+13,9) | 7. | |||
17 | R7 | 71,3 km | 2 | 553 mil. € | 5 | 5 | po 2040 (0,0) | 32. | |||
17 úsekov |
454,7 km |
2 - 6 |
5 775 mil. € |
4,1 |
3,9 |
10/2035 - po 2040 |
7. - 32. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku