dátum |
plánovaný
|
odhad NDS
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka | ||||||||
315,6 km |
2 - 8 |
40 |
6 244 mil. € |
2,7 |
|||||||||
1 | 12/2013 | D1 | 14,9 km | 4 | 3 | 341 mil. € | 449 - 869 | 1 | |||||
2 | 6/2014 | D1 | 13,5 km | 4 | 1 | 555 mil. € | 598 - 1 181 | 1 | |||||
3 | 3/2021 | R3 | 4,4 km | 2 | 2 | 70 mil. € | 262 - 312 | 2 | |||||
4 | 3. | 3/2022 | D1 | 3,5 km | 8 | 1 | 149 mil. € | 837 | 1 | dopravné, TEN-T | |||
5 | 7. | 2/2024 | D1 | 13,5 km | 4 | 2 | 1 235 mil. € | 422 - 799 | 1 | dopravné, TEN-T | |||
6 | 10. | 4/2024 | D1 | 3,8 km | 2 | 0 | 57 mil. € | 231 | 3 | ||||
7 | 12. | 7/2024 | R3 | 6,5 km | 2 | 1 | 70 mil. € | 204 - 321 | 2 | ostatné | |||
8 | 18. | 4/2025 | D1 | 1,1 km | 2 | 0 | 12 mil. € | 2 | |||||
9 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 1 | 77 mil. € | 2 | ostatné | ||||
10 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 1 | 199 mil. € | 159 - 204 | 2 | ostatné | |||
11 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 1 | 234 mil. € | 837 | 2 | dopravné, TEN-T | |||
12 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 2 | 321 mil. € | 459 - 530 | 3 | dopravné, TEN-T | |||
13 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 1 | 63 mil. € | 170 - 254 | 3 | TEN-T | |||
14 | 46. | 3/2029 | D1 | 7,3 km | 4 | 0 | 321 mil. € | 541 | 3 | TEN-T | |||
15 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 2 | 71 mil. € | 196 - 287 | 4 | variant TEN-T | |||
16 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 2 | 191 mil. € | 489 - 601 | 3 | variant TEN-T | |||
17 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 2 | 94 mil. € | 245 | 4 | ostatné | |||
18 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 4 | 129 mil. € | 142 - 209 | 3 | ostatné | |||
19 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 1 | 418 mil. € | 222 - 236 | 3 | TEN-T | |||
20 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 2 | 192 mil. € | 205 - 244 | 2 | TEN-T | |||
21 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 1 | 139 mil. € | 64 - 112 | 4 | TEN-T | |||
22 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 1 | 162 mil. € | 202 - 239 | 3 | TEN-T | |||
23 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 1 | 136 mil. € | 27 - 108 | 4 | ostatné | |||
24 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 2 | 305 mil. € | 3 | variant TEN-T | ||||
25 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 0 | 92 mil. € | 147 - 155 | 4 | variant TEN-T | |||
26 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | 6 | 611 mil. € | 62 - 372 | 4 | variant TEN-T | |||
315,6 km |
2 - 8 |
40 |
6 244 mil. € |
2,7 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku