dátum |
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 1 018 m | 173 mil. € | 12 387 - 17 316 | 2 | 3 | 5 | 4/2026 | 4/2026 (+3,7) | ||||
2 | 11. | 6/2024 | R1 | 2,7 km | 131 m | 155 mil. € | 16 268 | 4 | 3 | 11 | 6/2026 | 6/2026 (+3,5) | ||||
3 | 30. | 10/2026 | R1 | 4,6 km | 1 757 m | 100 mil. € | 11 611 | 4 | 3 | 30 | 10/2028 | 10/2028 (+3,5) | ||||
4 | 37. - 38. | 2/2028 | R1 | 14,9 km | 446 m | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 37 | 2/2031 | 2/2031 (+6,9) | ||||
5 | 55. - 56. | 5/2031 | R1 | 11,5 km | 428 m | 406 mil. € | 7 784 | 4 | 4 | 56 | 5/2033 | 5/2033 (+10,2) | ||||
6 | 55. - 56. | 5/2031 | R1 | 9,5 km | 366 m | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 55 | 5/2033 | 5/2033 (+10,2) | ||||
7 | 62. - 63. | 10/2032 | D2 | 8,5 km | 90 mil. € | 32 968 | . . . | 5 | 5 | 62 | 10/2035 | 10/2035 (+5,6) | ||||
8 | 62. - 63. | 10/2032 | D2 | 6,9 km | 107 mil. € | 5 | 5 | 61 | 10/2035 | 10/2035 (+5,9) | ||||||
9 | 71. - 78. | po 2040 | R1 | 42,1 km | 631 mil. € | 5 713 - 13 545 | 5 | 5 | 74 | po 2040 | po 2040 | |||||
9 úsekov |
108,9 km |
4 144 m |
2 785 mil. € |
5 713 - 32 968 | 4,0 |
3,9 |
5 - 74 |
4/2026 - po 2040 |
4/2026 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku