dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
prebratie
| |||||||
196,3 km |
2 - 6 |
2 876 mil. € |
2,9 |
|||||||||
1 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2/2017 | |||||
2 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 1 | 8/2017 | |||||
3 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 70 mil. € | 2 | 2/2016 | 2/2012 | |||
4 | 12. | 7/2024 | ![]() | R3 | 6,5 km | 2 | 70 mil. € | 2 | 5/2015 | 12/2022 | ||
5 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2/2016 | 1/2024 | ||
6 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | 199 mil. € | 2 | 2/2016 | 1/2024 | ||
7 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | 9/2009 | 7/2026 | ||
8 | 42. - 43. | 11/2028 | ![]() | R3 | 5,0 km | 2 | 63 mil. € | 3 | 5/2015 | 4/2026 | ||
9 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 5 | 9/2009 | 6/2028 | ||
10 | 48. - 49. | 9/2029 | ![]() | R3 | 7,9 km | 2 | 71 mil. € | 4 | 2/2016 | 2/2028 | ||
11 | 57. - 58. | 6/2031 | ![]() | R3 | 14,0 km | 4 | 191 mil. € | 3 | 2/2016 | 11/2029 | ||
12 | 60. - 61. | 8/2031 | ![]() | R3 | 8,7 km | 2 | 94 mil. € | 4 | 1/2030 | |||
13 | 60. - 61. | 8/2031 | ![]() | R3 | 10,9 km | 2 | 129 mil. € | 3 | 1/2030 | |||
14 | 69. - 70. | 8/2034 | ![]() | R3 | 14,0 km | 2 | 305 mil. € | 3 | 2/2016 | 2/2033 | ||
15 | 71. - 78. | po 2040 | ![]() | R3 | 10,3 km | 2 | 92 mil. € | 4 | 2/2016 | |||
16 | 71. - 78. | po 2040 | ![]() | R3 | 58,5 km | 2 | 611 mil. € | 4 | 5/2015 | |||
196,3 km |
2 - 6 |
2 876 mil. € |
2,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku