dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
| ||||||||
231,9 km |
2 - 6 |
28 |
2 805 mil. € |
3,7 |
4,2 |
|||||||||
1 | 7/2016 | D4 | 4,4 km | 4 - 6 | 2 | 1 | 2 | |||||||
2 | 7/2016 | D4 | 22,6 km | 4 - 6 | 6 | 1 | 2 | |||||||
3 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 2 | 191 mil. € | 4 | 5 | 5,0 | 11/2014 | |||
4 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 1 | 227 mil. € | 4 | 4 | 5,0 | 11/2014 | |||
5 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | 1 | 172 mil. € | 4 | 4 | 5,0 | 11/2014 | |||
6 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | 2 | 161 mil. € | 4 | 5 | 5,0 | 11/2014 | |||
7 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 1 | 772 mil. € | 3 | 4 | 8,0 | 9/2009 | |||
8 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 2 | 133 mil. € | 5 | 5 | 7,0 | 9/2009 | |||
9 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | 2 | 230 mil. € | 5 | 5 | 7,0 | 5/2016 | |||
10 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | 3 | 367 mil. € | 5 | 5 | 9,0 | 5/2016 | |||
11 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | 6 | 553 mil. € | 5 | 5 | 9,0 | 5/2016 | |||
231,9 km |
2 - 6 |
28 |
2 805 mil. € |
3,7 |
4,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku