plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
20 úsekov |
269,3 km |
2 - 4 |
3 921 mil. € |
5 189 - 50 895 | 3,2 |
3,5 |
6 - 69 |
7/2021 - 8/2037 | ||||||
1 | ![]() | R2 | 6,2 km | 2 | 105 mil. € | 5 304 | 1 416 | 2 | 2 | 8 | 3/2026 (+4,7) | |||
2 | ![]() | R2 | 9,6 km | 2 | 112 mil. € | 8 634 - 11 116 | 1 824 - 2 207 | 2 | 4 | 40 | 3/2031 (+5,9) | |||
3 | ![]() | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 1 253 - 1 628 | 5 | 5 | 48 | 9/2032 (+5,6) | |||
4 | ![]() | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 1 199 | 5 | 4 | 38 | 2/2031 (+4,1) | |||
5 | ![]() | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 1 373 - 6 905 | 3 | 3 | 6 | 7/2026 (+4,3) | |||
6 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 8 780 - 11 203 | 2 408 - 2 413 | 3 | 4 | 2024 (+2,8) | ||||
7 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 2 815 | 3 | 4 | 24 | 12/2028 (+4,3) | |||
8 | ![]() | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 1 774 - 2 440 | 4 | 4 | 26 | 4/2028 (+4,8) | |||
9 | ![]() | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 269 - 3 025 | 2 | 2 | 22 | 10/2028 (+3,2) | |||
10 | ![]() | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 1 815 - 1 961 | 3 | 5 | 33 | 12/2029 (+2,8) | |||
11 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 2 305 - 2 416 | 2 | 2 | 2021 (+1,1) | ||||
12 | ![]() | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 1 268 - 2 000 | 4 | 4 | 69 | 8/2037 (+5,9) | |||
13 | ![]() | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 1 482 - 1 790 | 4 | 4 | 29 | 8/2028 (+5,1) | |||
14 | ![]() | R2 | 11,5 km | 2 | 235 mil. € | 7 793 | 1 914 | 2 | 4 | 41 | 9/2031 (+5,4) | |||
15 | ![]() | R2 | 14,1 km | 2 | 272 mil. € | 5 792 - 7 064 | 1 175 - 1 286 | 3 | 2 | 17 | 12/2029 (+5,4) | |||
16 | ![]() | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 1 146 - 1 203 | 5 | 5 | 44 | 2/2032 (+4,9) | |||
17 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 2 829 | 3 | 4 | 23 | 10/2028 (+4,2) | |||
18 | ![]() | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 1 335 - 1 725 | 5 | 4 | 47 | 7/2032 (+5,3) | |||
19 | ![]() | R2 | 8,3 km | 2 | 169 mil. € | 5 277 - 6 250 | 1 466 - 1 525 | 2 | 2 | 13 | 8/2026 (+5,1) | |||
20 | ![]() | R2 | 17,5 km | 4 | 287 mil. € | 12 819 - 29 988 | 2 841 - 4 706 | 2 | 2 | 58 | 7/2034 (+10,0) | |||
20 úsekov |
269,3 km |
2 - 4 |
3 921 mil. € |
5 189 - 50 895 | 3,2 |
3,5 |
6 - 69 |
7/2021 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku