dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
269,3 km |
2 - 4 |
3 921 mil. € |
15,2 mil. € |
3,2 |
3,5 |
|||||||
1 | 8/2019 | R2 | 13,5 km | 4 | R 24,5/100 | 142 mil. € | 10,5 mil. € | 2 | 2 | |||
2 | 3/2020 | R2 | 9,1 km | 4 | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | 267 mil. € | 28,7 mil. € | 3 | 4 | |||
3 | 6. | 7/2023 | R2 | 6,8 km | 4 | R 24,5/100 | 171 mil. € | 25,1 mil. € | 3 | 3 | ||
4 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R 22,5/100, plánované v 1/2-profile | 105 mil. € | 17,0 mil. € | 2 | 2 | ||
5 | 13. | 8/2024 | R2 | 8,3 km | 2 | R 22,5/100, plánované v 1/2-profile | 169 mil. € | 20,3 mil. € | 2 | 2 | ||
6 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 272 mil. € | 19,3 mil. € | 3 | 2 | ||
7 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | 277 mil. € | 17,3 mil. € | 2 | 2 | ||
8 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 23,3 mil. € | 3 | 4 | ||
9 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 143 mil. € | 22,0 mil. € | 3 | 4 | ||
10 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 10,2 mil. € | 4 | 4 | ||
11 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | 125 mil. € | 11,8 mil. € | 4 | 4 | ||
12 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 224 mil. € | 12,5 mil. € | 3 | 5 | ||
13 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 73 mil. € | 8,9 mil. € | 5 | 4 | ||
14 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 112 mil. € | 11,7 mil. € | 2 | 4 | ||
15 | 41. | 9/2028 | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 20,4 mil. € | 2 | 4 | ||
16 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 176 mil. € | 9,8 mil. € | 5 | 5 | ||
17 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 117 mil. € | 8,4 mil. € | 5 | 4 | ||
18 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 9,5 mil. € | 5 | 5 | ||
19 | 59. | 7/2031 | R2 | 17,5 km | 4 | R 24,5/100 | 287 mil. € | 26,7 mil. € | 2 | 2 | ||
20 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 662 mil. € | 13,5 mil. € | 4 | 4 | ||
269,3 km |
2 - 4 |
3 921 mil. € |
15,2 mil. € |
3,2 |
3,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku