dátum |
plánovaný
|
odhad NDS
|
pozemky
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
12 úsekov |
153,3 km |
2 - 4 |
1 972 mil. € |
128,3 mil. € |
3,0 |
2,5 |
8/2017 - po 2040 |
|||||||
1 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 5,1 mil. € | 2 | 2 | 2/2025 | ||||
2 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 94 mil. € | 12,0 mil. € | 4 | 2 | 12/2030 | ||||
3 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 305 mil. € | 15,0 mil. € | 3 | 3 | 12/2033 | ||||
4 | 12. | 7/2024 | R3 | 6,5 km | 2 | 70 mil. € | 5,8 mil. € | 2 | 2 | 12/2023 | ||||
5 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 19,0 mil. € | 3 | 3 | 10/2030 | ||||
6 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 8,9 mil. € | 4 | 3 | 1/2029 | ||||
7 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 7,1 mil. € | 2 | 3 | 2/2025 | ||||
8 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 6,0 mil. € | 3 | 2 | 12/2030 | ||||
9 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 92 mil. € | 15,0 mil. € | 4 | 2 | |||||
10 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 5,7 mil. € | 2 | 2 | 8/2017 | |||||
11 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | 611 mil. € | 27,5 mil. € | 4 | 4 | po 2040 | ||||
12 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 63 mil. € | 1,3 mil. € | 3 | 2 | 3/2028 | ||||
12 úsekov |
153,3 km |
2 - 4 |
1 972 mil. € |
128,3 mil. € |
3,0 |
2,5 |
8/2017 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku