dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka | ||||||||||||
16 úsekov |
196,3 km |
2 - 6 |
2 876 mil. € |
3 247 - 93 344 | 2,9 |
|||||||||||
1 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 1/2007 | 6/2027 | |||||||
2 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 8/2007 | 2/2026 | |||||||
3 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | Dlhá nad Oravou | 77 mil. € | 2 | 7/1993 | 4/2010 | ||||||
4 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | Valaská Dubová, Likavka | 94 mil. € | 7 211 | 4 | 5/2007 | 4/2027 | |||||
5 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | Sklené,
Ráztočno | 305 mil. € | 3 | 3/2007 | 5/2030 | ||||||
6 | 7/2016 | D4 | 4,4 km | 4 - 6 | Čierna voda, Rača | 1 | 11/2014 | |||||||||
7 | 7/2016 | D4 | 22,6 km | 4 - 6 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 32 336 - 93 344 | . . . | 1 | 1/2015 | |||||||
8 | 12. | 7/2024 | R3 | 6,5 km | 2 | privádzač Krupina | 70 mil. € | 6 706 - 9 733 | 2 | 6/2008 | 10/2021 | |||||
9 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | Martin, Rakovo | 191 mil. € | 14 233 - 18 874 | 3 | 5/2008 | 11/2027 | |||||
10 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | Mošovce,
Horná Štubňa | 71 mil. € | 5 441 - 8 427 | 4 | 5/2008 | 7/2025 | |||||
11 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | Podbiel | 199 mil. € | 5 550 - 9 787 | 2 | 7/1993 | 2/2011 | |||||
12 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | Široká, Jasenová, v mestskom variante tiež Kocmáľ (Mokraď) a Dolný Kubín stred | 129 mil. € | 5 586 - 10 745 | 3 | 5/2007 | 4/2027 | |||||
13 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 92 mil. € | 5 098 - 5 557 | 4 | 5/2008 | |||||||
14 | 3/2021 | R3 | 4,4 km | 2 | Nižná,
Nižná - sever | 70 mil. € | 10 334 - 11 542 | 2 | 7/1993 | 9/2009 | ||||||
15 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | Budča, privádzače D. Niva, Babiná, Hont. Nemce, Dudince, Semerovce | 611 mil. € | 3 247 - 11 434 | 4 | 6/2008 | ||||||
16 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | Šahy | 63 mil. € | 9 492 - 10 279 | 3 | 6/2008 | 4/2025 | |||||
16 úsekov |
196,3 km |
2 - 6 |
2 876 mil. € |
3 247 - 93 344 | 2,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku