dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
246,8 km |
2 - 4 |
4 559 mil. € |
42,5 min. |
3,3 |
2,9 |
||||||||||
1 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 70 mil. € | 7,0 min. | 1 307 - 1 203 | 2 | 2 | 8/2006 | 2/2011 | |||
2 | 5. | 4/2023 | ![]() | R1 | 8,1 km | 4 | 173 mil. € | 775 - 1 092 | 2 | 3 | 4/2010 | 12/2019 | |||
3 | 11. | 6/2024 | ![]() | R1 | 2,7 km | 4 | 155 mil. € | 1 868 | 4 | 3 | 4/2010 | 1/2023 | |||
4 | 12. | 7/2024 | ![]() | R3 | 6,5 km | 2 | 70 mil. € | 1 175 - 1 262 | 2 | 2 | 11/2018 | 11/2021 | |||
5 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 5,5 min. | 2 | 2 | 8/2006 | 1/2023 | |||
6 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | 199 mil. € | 11,0 min. | 782 - 1 231 | 2 | 3 | 8/2006 | 1/2023 | ||
7 | 30. | 10/2026 | ![]() | R1 | 4,6 km | 4 | 100 mil. € | 1 066 | 4 | 3 | 4/2010 | 7/2025 | |||
8 | 37. - 38. | 2/2028 | ![]() | R1 | 14,9 km | 4 | 785 mil. € | 830 - 1 460 | 3 | 3 | 4/2010 | 3/2024 | |||
9 | 42. - 43. | 11/2028 | ![]() | R3 | 5,0 km | 2 | 63 mil. € | 1 111 - 1 112 | 3 | 2 | 11/2018 | 8/2026 | |||
10 | 48. - 49. | 9/2029 | ![]() | R3 | 7,9 km | 2 | 71 mil. € | 1 024 - 1 288 | 4 | 3 | 5/2019 | 2/2027 | |||
11 | 55. - 56. | 5/2031 | ![]() | R1 | 11,5 km | 4 | 406 mil. € | 940 | 4 | 4 | 4/2010 | 3/2029 | |||
12 | 55. - 56. | 5/2031 | ![]() | R1 | 9,5 km | 4 | 339 mil. € | 975 - 1 570 | 4 | 4 | 4/2010 | 3/2029 | |||
13 | 57. - 58. | 6/2031 | ![]() | R3 | 14,0 km | 4 | 191 mil. € | 2 114 - 2 070 | 3 | 3 | 9/2010 | 9/2029 | |||
14 | 60. - 61. | 8/2031 | ![]() | R3 | 8,7 km | 2 | 94 mil. € | 7,5 min. | 919 | 4 | 2 | 1/2029 | |||
15 | 60. - 61. | 8/2031 | ![]() | R3 | 10,9 km | 2 | 129 mil. € | 11,5 min. | 791 - 1 514 | 3 | 2 | 1/2029 | |||
16 | 69. - 70. | 8/2034 | ![]() | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 2/2020 | 2/2032 | ||||
17 | 71. - 78. | po 2040 | ![]() | R1 | 42,1 km | 4 | 631 mil. € | 644 - 1 514 | 5 | 5 | |||||
18 | 71. - 78. | po 2040 | ![]() | R3 | 10,3 km | 2 | 92 mil. € | 1 155 - 1 257 | 4 | 2 | 9/2010 | ||||
19 | 71. - 78. | po 2040 | ![]() | R3 | 58,5 km | 2 | 611 mil. € | 616 - 1 456 | 4 | 4 | 11/2018 | ||||
246,8 km |
2 - 4 |
4 559 mil. € |
42,5 min. |
3,3 |
2,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku