dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
32 úsekov |
422,6 km |
2 - 4 |
53 363 m |
5 892 mil. € |
3,1 |
3,1 |
|||||||
1 | 8/2019 | R2 | 13,5 km | 4 | 1 631 m | 142 mil. € | 2 | 2 | 6/2018 | ||||
2 | 3/2020 | R2 | 9,1 km | 4 | 2 553 m | 267 mil. € | 3 | 4 | |||||
3 | 3/2021 | R3 | 4,4 km | 2 | 1 568 m | 70 mil. € | 2 | 2 | 2/2012 | ||||
4 | 6. | 7/2023 | R2 | 6,8 km | 4 | 1 556 m | 171 mil. € | 3 | 3 | 3/2022 | |||
5 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 343 m | 105 mil. € | 2 | 2 | 4/2022 | |||
6 | 12. | 7/2024 | R3 | 6,5 km | 2 | 1 463 m | 70 mil. € | 2 | 2 | 12/2022 | |||
7 | 13. | 8/2024 | R2 | 8,3 km | 2 | 401 m | 169 mil. € | 2 | 2 | 8/2022 | |||
8 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 1 035 m | 272 mil. € | 3 | 2 | 7/2023 | |||
9 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 1 544 m | 77 mil. € | 2 | 2 | 1/2024 | |||
10 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 2 764 m | 199 mil. € | 2 | 3 | 1/2024 | |||
11 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 1 433 m | 277 mil. € | 2 | 2 | 5/2024 | |||
12 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 145 m | 59 mil. € | 3 | 4 | 8/2023 | |||
13 | 24. | 12/2025 | R2 | 6,1 km | 4 | 1 462 m | 143 mil. € | 3 | 4 | 2/2024 | |||
14 | 26. | 4/2026 | R2 | 20,7 km | 2 | 2 594 m | 211 mil. € | 4 | 4 | 8/2024 | |||
15 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 1 041 m | 125 mil. € | 4 | 4 | 3/2025 | |||
16 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 554 m | 224 mil. € | 3 | 5 | 12/2024 | |||
17 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 397 m | 73 mil. € | 5 | 4 | 2/2026 | |||
18 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 1 157 m | 112 mil. € | 2 | 4 | 8/2026 | |||
19 | 41. | 9/2028 | R2 | 11,5 km | 2 | 2 549 m | 235 mil. € | 2 | 4 | 2/2027 | |||
20 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 652 m | 63 mil. € | 3 | 2 | 4/2026 | |||
21 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 1 739 m | 176 mil. € | 5 | 5 | 1/2027 | |||
22 | 47. | 7/2029 | R2 | 14,0 km | 2 | 768 m | 117 mil. € | 5 | 4 | 7/2027 | |||
23 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 1 074 m | 93 mil. € | 5 | 5 | 9/2027 | |||
24 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 820 m | 71 mil. € | 4 | 3 | 2/2028 | |||
25 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 1 024 m | 191 mil. € | 3 | 3 | 11/2029 | |||
26 | 59. | 7/2031 | R2 | 17,5 km | 4 | 2 230 m | 287 mil. € | 2 | 2 | 9/2029 | |||
27 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 178 m | 94 mil. € | 4 | 2 | 1/2030 | |||
28 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 1 040 m | 129 mil. € | 3 | 2 | 1/2030 | |||
29 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 2 641 m | 305 mil. € | 3 | 3 | 2/2033 | |||
30 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 2 587 m | 662 mil. € | 4 | 4 | 2/2033 | |||
31 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 95 m | 92 mil. € | 4 | 2 | ||||
32 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | 12 326 m | 611 mil. € | 4 | 4 | ||||
32 úsekov |
422,6 km |
2 - 4 |
53 363 m |
5 892 mil. € |
3,1 |
3,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku