dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
skutočnosť podľa zmluvy
| |||||||||
11 úsekov |
83,9 km |
2 - 4 |
19 393 m |
1 604 mil. € |
2 552 - 50 895 | 2,5 |
2,6 |
||||||||
1 | 1. | 10/2021 | R4 | 14,3 km | 4 | 1 036 m | 202 mil. € | 10 088 - 50 895 | 2 | 1 | |||||
2 | 4. | 9/2022 | R4 | 10,2 km | 4 | 1 432 m | 299 mil. € | 22 341 - 30 731 | 1 | 3 | |||||
3 | 7/2019 | R4 | 4,3 km | 4 | 884 m | 179 mil. € | 15 837 - 18 098 | 1 | 3 | 7/2019 | |||||
4 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 1 468 m | 105 mil. € | 14 625 | 2 | 2 | |||||
5 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 2 104 m | 116 mil. € | 6 651 - 9 113 | 2 | 3 | |||||
6 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 2 907 m | 133 mil. € | 5 814 - 7 518 | 4 | 3 | |||||
7 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 1 017 m | 101 mil. € | 3 782 - 6 302 | 4 | 3 | |||||
8 | 19. | 6/2025 | R4 | 8,2 km | 2 | 453 m | 94 mil. € | 4 001 | 3 | 3 | |||||
9 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 1 826 m | 124 mil. € | 3 769 - 3 897 | 3 | 3 | |||||
10 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 1 721 m | 122 mil. € | 3 407 - 3 769 | 2 | 2 | |||||
11 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 4 546 m | 129 mil. € | 2 552 - 2 737 | 4 | 3 | |||||
11 úsekov |
83,9 km |
2 - 4 |
19 393 m |
1 604 mil. € |
2 552 - 50 895 | 2,5 |
2,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku