dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
11 úsekov |
83,9 km |
2 - 4 |
1 604 mil. € |
2,5 |
2,6 |
|||||||||
1 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | Kuková | 116 mil. € | 2 | 3 | 5,7 | ||||
2 | 1. | 10/2021 | R4 | 14,3 km | 4 | Košice-juh, Krásna, Hrašovík | 202 mil. € | 2 | 1 | 0,1 | ||||
3 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | Kuková | 133 mil. € | 4 | 3 | 8,6 | ||||
4 | 19. | 6/2025 | R4 | 8,2 km | 2 | Svidník sever | 94 mil. € | 3 | 3 | 3,7 | ||||
5 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | Lipníky | 105 mil. € | 2 | 2 | 4,9 | ||||
6 | 7/2019 | R4 | 4,3 km | 4 | Prešov - sever | 179 mil. € | 1 | 3 | 0,0 | |||||
7 | 4. | 9/2022 | R4 | 10,2 km | 4 | Kapušany | 299 mil. € | 1 | 3 | 1,0 | ||||
8 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | Giraltovce | 124 mil. € | 3 | 3 | 8,6 | ||||
9 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | Okrúhle | 122 mil. € | 2 | 2 | 5,7 | ||||
10 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | Stročín | 101 mil. € | 4 | 3 | 8,6 | ||||
11 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | Hunkovce, Vyšný Komárnik | 129 mil. € | 4 | 3 | 7,1 | ||||
11 úsekov |
83,9 km |
2 - 4 |
1 604 mil. € |
2,5 |
2,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku