dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||
1 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 454 - 531 | 5 | 4 | 7/2032 (+5,3) | |||
2 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 359 - 396 | 5 | 5 | 2/2032 (+4,9) | |||
3 | 12/2017 | D1 | 2,6 km | 4 | 39 mil. € | 800 | 1 | 1 | 2021 (+2,2) | ||||
4 | 6/2017 | D1 | 7,9 km | 4 | 434 mil. € | 1 228 - 1 350 | 1 | 2 | 7/2021 (0,0) | ||||
5 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 423 - 703 | 4 | 3 | 9/2032 (+4,1) | |||
6 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 473 - 644 | 5 | 5 | 9/2032 (+5,6) | |||
7 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2033 (+4,5) | ||||
8 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 974 | 3 | 3 | 9/2033 (+5,8) | |||
8 úsekov |
71,0 km |
2 - 4 |
1 383 mil. € |
3,6 |
3,5 |
7/2021 - 9/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku